Page 95 - SAC - DCD - AMB 03 09 20
P. 95
Permit and Service Delivery — Performance Standards + Process Guide City of Encinitas
outstanding issues with the supervisor. Schedule a PIR conference
with the project applicant, technical team and property owner (if TI O N 9
different) to discuss remaining issues and develop a plan to move the
project forward to decision. E C
S
4 Cycle Review #4
Follow the same procedures listed in Cycle Review #2.
5 Cycle Review CEQA
n Make Environmental Determination. The Environmental
Coordinator must make an environmental determination within
30 days of the date the application is deemed complete. If the
project is determined to be exempt from environmental review,
the Environmental Project Manager must update the application
environmental status on e-Project Source to ‘Exempt’. If an initial