Permit and Service Delivery — Performance Standards + Process Guide              City of Encinitas




                       outstanding issues with the supervisor. Schedule a PIR conference
                       with the project applicant, technical team and property owner (if                                 TI O N 9
                       different) to discuss remaining issues and develop a plan to move the
                       project forward to decision.                                                                      E C
                                                                                                                         S
                  4        Cycle Review #4





                    Follow the same procedures listed in Cycle Review #2.



                  5        Cycle Review CEQA





                      n	 Make Environmental Determination. The Environmental
                        Coordinator must make an environmental determination within
                        30 days of the date the application is deemed complete. If the
                        project is determined to be exempt from environmental review,
                        the Environmental Project Manager must update the application
                        environmental status on e-Project Source to ‘Exempt’. If an initial