Page 53 - UL_Report On_Part 1
P. 53

43 IITGN-UL/Façade  44 IITGN-UL/Façade






 (d) Role of POP and cement boards in providing fire protection to   Cement boards did not allow structural  temperature  to rise near
 deck slab   beam and slab sections  thus protecting from direct fire exposure.
             After 6 min from ignition, maximum temperature at roof level was
             685°C whereas near steel beam beneath cement board it was 25°C.
 •  Material properties of POP and cement board  Major failure of cement boards at ground level was observed around
 Deck slab and structural beams were provided with double layer of fire protection   10.5 minutes during flashover when  temperatures reached around
 through POP sheets and cement boards. Deck slab is covered with 12 mm thick POP   800°C.
 sheets of size 3’ x 3’. Joints between sheets are filled with POP paste.  Cement boards at first floor level failed locally at around 12 minutes
 Beam sides and bottom were covered through 18mm thick cement boards of size 8’ x 4’   and major failure was observed around 17 minutes  thus exposing
 fixed to MS square pipe sections below roof frame.MS Square pipe section of 1” x 1” x   members  to direct heat. Cement boards at second floor level were
 1.6mm  thick @ 2’ spacing were provided at roof level  throughout all compartments   intact as fire failed to propagate at higher level from first floor.
 (refer Figure 24). Cement boards were installed through SDS type 1” screws fixed at an   Closed spacing of screws during installation helped cement boards to
 interval of 8” c/c and gaps between cement boards were filled with POP paste.
             avoid premature failures.  Workmanship during structural fire
             protection  is  important. Thickness  of  cement boards  also  plays  an
             important role in providing resistance to exposed fire.                        Image 9: Local failure of cement boards at ground floor level


 ACP  ACP
 CLADING  ELEVATION-3  CLADDING

 +  +  +  +  +  +  +  +
 + + + +  + + + +
 +
 + + + + +  +  + +  + +  + +  + +
 +
 + + + + +                                                                                                                                     POP sheet
 + + +
 + + +
 + + + + +
 + + + + +  +
 +
 +
 + + + + +
 + + +
 610  610
 CABIN-2  610  2320  Cement board
 610  UP  ELEVATION-2                                                                                    8’’ spacing
 610
 610  CABIN-1
 610
 ELEVATION-4
 610
 610
 CABIN-3
 610
 +  +  +  +                                                                                                                                    MS square pipe
 + + + +  610          SDS Screw
 + +  + + + +  + +
 +
 +
 +
 ms pipe 1 x 1 x 1.6 mm thick  + + + + +  +  + + + + +  +  +                                                                                   1’’ x 1’’ x 1.6mm
 + + + + +
 + + +  + + + + ++  + +
 + + +  + + +
 + + + + +
 + + + + +
 ACP  ACP
 CLADING  CLADING
 Figure 24: MS Pipe layout for fixing cement boards at all floor levels
                                                                  Image 10: Local failure of cement boards at first floor level
   48   49   50   51   52   53   54   55   56   57   58