Page 50 - UL_Report On_Part 1
P. 50

41 IITGN-UL/Façade                                                                                                                                                           42 IITGN-UL/Façade











              18:32:00 Ground floor                                                                  First floor                    Second floor                                                                                                                                 Glass panel at first floor had fallen.
                                                                                                                                                                                            5.45 min                    Cement boards at ground floor still intact.              Max roof temperature at first floor
                                                                                                                                                                                                                                                                                          is about 280°C
                -5 min                          Data acquisition started

                                                                                                                                                                                                                                                                                  ACP sheets at first floor catch fire.
                0 min               Wooden crib placed outside compartment 1 is ignited                                                                                                     6.5 min             Temperature near steel beam is about 60°C indicating local       Maximum temperature at first floor

                                        Flames penetrate into the GF compartment                                                                                                                                                failure of cement board                                  is around 340°C
                2.2 min
                                               through ventilation opening
                                                                                                                                                                                                            Flashover occurs during this interval. Max roof temp. is around 816°C.  All ACP sheets & glass panels      Second floor roof level
                                    Cotton curtains catch fire and max temp recorded is                                                                                                     10.5 min       Major failure of cement boards allowing temp to rise near beam around    have fallen. Maximum temp.       temperature around 54°C
               2.75 min                                                                                                                                                                                    120°C. Aluminium framework has melted completely at certain locations
                                                 by TC 22 around 200°C                                                                                                                                                                                                                  at roof level is 307°C
                                 Halogen lights are burnt. Smoke obscuration has increased.                                                                                                                 Temp. begins to reduce as all fuel within compartment is consumed.
               3.03 min                                                                                                                                                                     11.62 min                                                                                 Local failure of cement
                                            Max. temp by TC 22 is about 310°C                                                                                                                                 Temp. near steel beam is about 150°C whereas roof temp. is 710°C             board occurs

                                     Fire start to spread off through curtains increasing                  Lights at first and
               3.13 min                                                                                  second floor are burnt                                                                                                                                                  Flashover occurs at first floor level.
                                               temperature around 400°C                                                                                                                                                                                                            Max roof temp is around 675°C.  Fire has still not propagated to
                                                                                                                                                                                           16.67 min        Fire dies out due to inadequacy of fuel. Reduced temp. is about 305°C  Major failure of cement board thereby  second floor. Temp.
               3.33 min          Max. roof temp is about 550°C whereas near beam beneath                                                                                                                                                                                                                                   is about 56°C
                                              cement board is around 19°C.                                                                                                                                                                                                      increasing temp from 220°C to 510°C.

                3.5 min                  ACP at ground level has not caught fire.                                                                                                          18.55 min                                                                                                               Fire propagates to second floor.
                                                                                                                                                                                                                                                                                                                     Max temp is about 226°C
                                           Temp at base level increased to 40°C
                                                                                                                                                                                           21.83 min                           Fire extinguishing begins                             Fire extinguishing begins       Fire extinguishing begins
                                   Wooden crib placed within compartment catches fire.                     Fire penetrating at
               3.67 min          Glass panel has fallen in intact form due to failure of binder.         first floor level through
                             Max roof temp near façade is 675°C whereas at base is around 50°C.             leap frog effect

                            Three glass panels fall in intact form enhancing ventilation conditions.
               4.95 min      Max temp at roof level is about 740°C (>660°C) leading to melting of        Max temp at first floor
                                                                                                          level is around 190°C
                                             aluminium cladding framework.                                                                                                                                                                Table 4: Timeline of events at all floor levels during fire Test 1
   45   46   47   48   49   50   51   52   53   54   55