                                                                                                  Features
                                                                                                                 1
                                                                                     Chapter 1: Introduction

                              Area Alarm Rough-In Assembly

                              The Area Alarm Rough-In Assembly consists of the rough-in assembly (R),
                              Breakout P.C. Board (N), mounting brackets (BN), and power supply. The
                              power supply includes the following (see figure 1-9 on page 1-19):
                               • Ground terminal (O)

                               • Terminal block (P)
                               • Power supply covers (S, T)

                               • On/Off switch (U)
                               • Fuse holder (V)

                               • Transformer (Q)

                                           Figure 1-9.  Area Alarm Rough-In






































                              NOTE:
                              The mounting brackets are not attached when they are shipped. Attach them
                              prior to installation. For more information about installing an original alarm
                              network, refer to the MedPlus TotalAlert™ Alarm Network Installation
                              Instructions (is550).