SCOPE AND ADMINISTRATION
[A] 109.4.6 Prosecution of violation. If the notice of vio- [A] 110.4 Revocation. The code official is authorized to, in
lation is not complied with promptly, the code official is writing, suspend or revoke a certificate of occupancy or com-
authorized to request the legal counsel of the jurisdiction pletion issued under the provisions of this code wherever the
to institute the appropriate proceeding at law or in equity certificate is issued in error, on the basis of incorrect informa-
to restrain, correct or abate such violation, or to require the tion supplied, or where it is determined that the building or
removal or termination of the unlawful occupancy of the structure, premise or portion thereof is in violation of any
building or structure in violation of the provisions of this ordinance or regulation or any of the provisions of this code.
code or of the order or direction made pursuant thereto.
[A] 109.4.7 Violation penalties. Persons who shall violate
a provision of this code or shall fail to comply with any of SECTION 111
the requirements thereof or who shall erect, install, alter, TEMPORARY STRUCTURES AND USES
repair or do work in violation of the approved construction [A] 111.1 General. The code official is authorized to issue a
documents or directive of the code official, or of a permit permit for temporary structures and temporary uses. Such
or certificate used under provisions of this code, shall be permits shall be limited as to time of service, but shall not be
guilty of a [SPECIFY OFFENSE], punishable by a fine of not permitted for more than 180 days. The code official is autho-
more than [AMOUNT] dollars or by imprisonment not rized to grant extensions for demonstrated cause.
exceeding [NUMBER OF DAYS], or both such fine and [A] 111.2 Conformance. Temporary structures and uses
imprisonment. Each day that a violation continues after shall conform to the structural strength, fire safety, means of
due notice has been served shall be deemed a separate egress, accessibility, light, ventilation and sanitary require-
offense. ments of this code as necessary to ensure the public health,
[A] 109.4.8 Abatement of violation. In addition to the safety and general welfare.
imposition of the penalties herein described, the code offi- [A] 111.3 Termination of approval. The code official is
cial is authorized to institute appropriate action to prevent authorized to terminate such permit for a temporary structure
unlawful construction or to restrain, correct or abate a vio- or use and to order the temporary structure or use to be dis-
lation; or to prevent illegal occupancy of a structure or continued.
premises; or to stop an illegal act, conduct of business or
occupancy of a structure on or about any premises.
SECTION 112
FEES
SECTION 110 [A] 112.1 Fees. A permit shall not be issued until the fees
CERTIFICATE OF COMPLETION
prescribed in Section 112.2 have been paid, nor shall an
[A] 110.1 General. A building, structure or premises shall amendment to a permit be released until the additional fee, if
not be used or occupied, and a change in the existing use or any, has been paid.
occupancy classification of a building, structure, premise or
portion thereof shall not be made until the code official has [A] 112.2 Schedule of permit fees. A fee for each permit
issued a certificate of completion therefor as provided herein. shall be paid as required, in accordance with the schedule as
The certificate of occupancy shall not be issued until the cer- established by the applicable governing authority.
tificate of completion indicating that the project is in compli- [A] 112.3 Work commencing before permit issuance. Any
ance with this code has been issued by the code official. person who commences any work before obtaining the neces-
sary permits shall be subject to an additional fee established
[A] 110.2 Certificate of occupancy. Issuance of a certificate
of occupancy shall not be construed as an approval of a viola- by the applicable governing authority, which shall be in addi-
tion of the provisions of this code or of other pertinent laws tion to the required permit fees.
and ordinances of the jurisdiction. Certificates presuming to [A] 112.4 Related fees. The payment of the fee for the con-
give authority to violate or cancel the provisions of this code struction, alteration, removal or demolition of work done in
or other laws or ordinances of the jurisdiction shall not be connection to or concurrently with the work or activity autho-
valid. rized by a permit shall not relieve the applicant or holder of
the permit from the payment of other fees that are prescribed
Exceptions:
by law.
1. Certificates of occupancy are not required for work
exempt from permits under Section 107.3. [A] 112.5 Refunds. The applicable governing authority is
authorized to establish a refund policy.
2. Accessory structures.
[A] 110.3 Temporary occupancy. The code official is
authorized to issue a temporary certificate of occupancy SECTION 113
before the completion of the entire work covered by the per- SERVICE UTILITIES
mit, provided that such portion or portions shall be occupied [A] 113.1 Connection of service utilities. No person shall
safely. The code official shall set a time period during which make connections from a utility, source of energy, fuel or
the temporary certificate of occupancy is valid. power to any building or system that is regulated by this code
8 2015 INTERNATIONAL WILDLAND-URBAN INTERFACE CODE
Copyrighted © 2014 by, or licensed to, ICC (ALL RIGHTS RESERVED); licensed to UL, LLC pursuant to License Agreement with ICC. No further reproductions authorized or distribution authorized.
ANY UNAUTHROIZED REPRODUCTION OR DISTRIBUTION IS A VIOLATION OF THE FEDERAL COPYRIGHT ACT AND THE LICENSE AGREEMENT; AND SUBJECT TO CIVIL AND CRIMINAL PENALTIES THEREUNDER.