Page 44 - Rice & Gardner Training Booklet - Distribute Copy R1
P. 44
07|Topic 7
Are we okay or not okay? What do you know, and how do you know it?
NOTES: D. WHY ARE TWO WEEK LOOK AHEAD SCHEDULES IMPORTANT?
The purpose of the two week look-ahead schedule is to plan labor activities
and goals for the next two weeks. The focus is on the overall project
schedule provided by the general contractor and the critical path schedule
created by the project manager. The two week look ahead schedule is to
ensure that projects are meeting or beating the estimated hours,
controlling overall costs, and maintaining the production schedule.
There are several purposes for and reasons why you should implement a
look-ahead schedule:
Maintain job schedules
Beat labor budgets
Plan manpower, materials, and tools required for task completion
Note information required for field supervision
Note coordination needed from the General Contractor or other
trades
3-Week Look Ahead Schedule
MAY 2017 RICE & GARDNER | 39
PROGRAM MANAGEMENT | GUIDE BOOK