New York Presbyterian Queens

                                                Chiller Replacement, Flushing, NY



































          SCHEDULE                 CONTRACT TYPE            REFERENCE
          6 Months                 Construction Manager-at-Risk  Vito Cassata, Vice President
                                                            718.670.1895
          COMPLETION DATE          OWNER
          2016                     New York Presbyterian Queens ARCHITECT
                                                            Everactive Solutions






                                                                      PROJECT DETAILS
         Th  e New York Presbyterian Queens project featured replacing two       •   Th  e three new chiller absorbers were rigged into
         existing gas fi red chillers along with the existing piping and controls   the building by crane and removed the existing
         related to these machines. Installed three new gas fi red chillers with all   louvers and reinstalled them for access to the
         related piping, controls, and electrical work. Th  e chemical treatment   chiller mechanical room.
         and sand fi lter system for the chillers was also relocated and upgraded.