New York Presbyterian Queens
Chiller Replacement, Flushing, NY
SCHEDULE CONTRACT TYPE REFERENCE
6 Months Construction Manager-at-Risk Vito Cassata, Vice President
718.670.1895
COMPLETION DATE OWNER
2016 New York Presbyterian Queens ARCHITECT
Everactive Solutions
PROJECT DETAILS
Th e New York Presbyterian Queens project featured replacing two • Th e three new chiller absorbers were rigged into
existing gas fi red chillers along with the existing piping and controls the building by crane and removed the existing
related to these machines. Installed three new gas fi red chillers with all louvers and reinstalled them for access to the
related piping, controls, and electrical work. Th e chemical treatment chiller mechanical room.
and sand fi lter system for the chillers was also relocated and upgraded.