Page 23 - BarrandBarr_135 W 50th Street HVAC Cooling Tower_7.28.17
P. 23
Barr & Barr 2nd Quarter Apr 4/2
0% 0% 0% 0% 0%
0% 0% 0%
Mar
Feb
Deadline
1st Quarter Jan
Dec
0%
0% Project Summary External Milestone
Nov External Tasks
4th Quarter Oct
Sep Summary Progress
Milestone Summary
Aug
Page 2
3rd Quarter Jul
Predecessors 52 51 54 44 56 54 58 58 58 61 63 Baseline Baseline Split Baseline Milestone
Mon 3/19/18 Thu 3/15/18 Mon 3/19/18 Mon 11/27/17 Mon 12/4/17 Thu 3/22/18 Tue 3/27/18 Tue 3/27/18 Mon 3/26/18 Mon 4/2/18 Mon 4/2/18
Finish
Tue 3/6/18 Fri 3/2/18 Fri 3/16/18 Tue 11/7/17 Fri 3/16/18 Fri 3/23/18 Fri 3/23/18 Fri 3/23/18 Wed 3/28/18 Mon 4/2/18
Start Tue 11/28/17
Duration 10 days 10 days 2 days 15 days 5 days 5 days 3 days 3 days 2 days 4 days 0 days Task Split Task Progress
Critical Critical Split Critical Progress
Cooling Tower Replacement 135 W 50th St. Task Name ID HVAC Insulation 53 HVAC BMS Roughing 54 HVAC Balancing 55 ELE Risers & Panels 56 ELE Equipt & Power Roughing 57 Equipment Startup 58 Punchlist 59 60 MEP Commissioning 61 Mechanical Finishes 62 Owner Training & Closeout 63 64 CONSTRUCTION COMPLETE Barr & Barr Date: Thu 7/27/17