Page 27 - BarrandBarr_135 W 50th Street HVAC Cooling Tower_7.28.17
P. 27
Item Item Included in Excluded from Total Cost
No. General General
Conditions Conditions
8 Project Accountant* $ 11,772
9 Clerical Staff* $ 11,908
10 Plan Coordinator* $ 10,268
11 Scheduling Staff* $ 0
12 Laborers* $ 0
13 Operating Engineers * $ 0
14 Field Office & Furniture $ 3,250
15 Telephone, Fax $ 3,250
16 Misc. Stationary & Office Supplies $ Included
17 Incidental Photocopy $ Included
18 Messenger Service $ Included
19 Postage, Federal Express $ 700
20 Printing of all Drawings, $
Specifications, and other
Approved Reproductions
21 General Cleaning $
22 Final Clean $
23 Protection Paper, Tools, Etc. $
24 Overtime Deliveries $
25 Overtime Shutdowns $
26 Rubbish Removal $
27 Equipment Rental $
28 Vehicle Rental N/A $ 0
29 Mileage Allowance $
30 Temporary hand tools $
31 Taxes $ Included
32 Permits $
33 Insurance $ Included
34 Elevator Reservation $
Management
35 Utility Consumption $
36 Inspections, Tests, and Approvals $
37 Debris Removal $
38 Computer Equipment and $
Services Used at Field Office 6,539
39 Photos and Video $ 300
40 Storage Containers $
th
135 W 50 Street Construction Manager RFP | PAGE 15