Page 25 - BarrandBarr_135 W 50th Street HVAC Cooling Tower_7.28.17
P. 25
Document management
Means & Methods management; Safety management
Materials testing management
Close-Outs & Sign-Offs
And all processes incidental to the above for a complete Project from Mobilization to
Close-Out
Contract Time Duration:
This solicitation should be based on the following time durations:
Pre-construction Advisory Services: 8/1/17-10/1/17
Management of All Construction Related Processes: 11/1/17-4/1/18