Page 25 - BarrandBarr_135 W 50th Street HVAC Cooling Tower_7.28.17
P. 25

 Document management
                     Means & Methods management; Safety management
                     Materials testing management
                     Close-Outs & Sign-Offs
                     And all processes incidental to the above for a complete Project from Mobilization to
                       Close-Out




               Contract Time Duration:


               This solicitation should be based on the following time durations:

               Pre-construction Advisory Services: 8/1/17-10/1/17

               Management of All Construction Related Processes: 11/1/17-4/1/18


















































                                                                     th
                                                            135 W 50  Street Construction Manager RFP | PAGE 13