d.  All transportation, lodging, meals, reasonable relocation expenses including tax gross-ups,
                   and subsistence expenses of Construction Manager’s employees incurred in discharge of
                   duties connected with performance of the Work, including travel to and from the homes of
                   Personnel to the Project site.

               NOTE: All trade and sub consultant costs should be EXCLUDED from General Conditions.

            Changes


               Indicate your markup with regard to additional costs for changes in scope below:

                Item     Item                                                               Percentage
                No.
                1        Fee on change orders                                                   2.5       %
                2        General conditions                       Excluding all items in                  %
                                                                  General Conditions            7.5
                                                                  matrix above
                3        Insurance                                                              1.5       %



               Additional Comments
               The bidder may include any additional information that may be deemed appropriate to enhance
               the bid response. Please be advised that all sections of this bid proposal form and associated
               documents must be completed in full. Failure to do so will result in a disqualification of the Bid
               Response.

               Acceptance
               We fully acknowledge that we have read the entire request for proposal which includes the
               instruction to bidders, Construction Documents, project description, and the bid proposal form.
               As part of our bid proposal we shall comply with all rules, regulations and requirements of the
               project team for the duration of this project.



               Agreed To:




               Signature: _____________________________________

                           Barr and Barr Inc.
               Company: _____________________________________

                             7/28/2017
               Date:        _____________________________________


                                                                     th
                                                            135 W 50  Street Construction Manager RFP | PAGE 17
   24   25   26   27   28   29   30