d. All transportation, lodging, meals, reasonable relocation expenses including tax gross-ups,
and subsistence expenses of Construction Manager’s employees incurred in discharge of
duties connected with performance of the Work, including travel to and from the homes of
Personnel to the Project site.
NOTE: All trade and sub consultant costs should be EXCLUDED from General Conditions.
Changes
Indicate your markup with regard to additional costs for changes in scope below:
Item Item Percentage
No.
1 Fee on change orders 2.5 %
2 General conditions Excluding all items in %
General Conditions 7.5
matrix above
3 Insurance 1.5 %
Additional Comments
The bidder may include any additional information that may be deemed appropriate to enhance
the bid response. Please be advised that all sections of this bid proposal form and associated
documents must be completed in full. Failure to do so will result in a disqualification of the Bid
Response.
Acceptance
We fully acknowledge that we have read the entire request for proposal which includes the
instruction to bidders, Construction Documents, project description, and the bid proposal form.
As part of our bid proposal we shall comply with all rules, regulations and requirements of the
project team for the duration of this project.
Agreed To:
Signature: _____________________________________
Barr and Barr Inc.
Company: _____________________________________
7/28/2017
Date: _____________________________________
th
135 W 50 Street Construction Manager RFP | PAGE 17