Page 24 - BarrandBarr_135 W 50th Street HVAC Cooling Tower_7.28.17
P. 24

BID RESPONSE FORM


               Project:    135 West 50  Street | HVAC Cooling Tower Replacement
                                    th

               Date Submitted:   7/28/2017


               Submitted By:   Barr and Barr Inc.


                                                       PROPOSAL


               Qualifications:
               Your bid response must address all the points identified below.  Failure to comply may result in
               your firm’s disqualification from the selection process.

                         Provide an organizational chart for this project. Submit the resumes of proposed key
                          project personnel and their roles.  List current project assignments including
                          anticipated completion dates.
                         Provide a list of proposed subcontractors.

                         Provide a proposed project milestone schedule (Gantt chart format).


               Purpose of this Bid Solicitation:

               Ownership wishes to engage a qualified NYC Construction Management firm through AIA
               Contract Forms A102/201-2007 to provide:

               1) Pre-construction Advisory Services consisting of (but not necessarily limited to):
                    Plan reviews
                    Cost estimating
                    Scheduling
                    Value Engineering
                     Sequencing Advice, Work Area Plans, Staging Plans
                    Logistics Planning
                     Subcontractor Bidding & Leveling
                     Establishment of the GMP – Including Allowances & Contingencies
                     Ordering of long-lead items

               2) Management of All Construction Related Processes consisting of (but not necessarily limited
               to):
                     All General Conditions and Supervision
                     Permitting (including DOB, DOT, etc.)
                     Negotiation of Sub-Contractor Pricing & Sub-Contracts
                     Submittal processes; Scheduling; All coordination of Trades; Cost tracking
                     Management of Applications for Payment