Page 26 - BarrandBarr_135 W 50th Street HVAC Cooling Tower_7.28.17
P. 26
Proposed Fees, Costs, and Markups:
Item Phase Proposed Fee
No.
1 Pre-construction services (flat fee for 2 $
months) 15,000
2 General conditions ( estimated for 5 $
months) 219,581
Total $
CM fee as a percentage markup of %
direct costs, plus approved general 2.5
conditions
Insurance percentage markup of direct %
costs, plus approved general conditions 1.5
Barr and Barr will return 100% of any savings realized in the G.M.P. 100% total transparency in
reporting and billing
financial
Construction Budget
This solicitation should be based on a projected total hard cost construction budget range of
$3,000,000.00 to $4,000,000.00.
General Conditions
Indicate below whether the following items are included or excluded in the general conditions
proposed above in Item #2. In order to minimize turnaround time and to facilitate an equal
comparison of proposals, please do not deviate from the requested format.
Item Item Included in Excluded from Total Cost
No. General General
Conditions Conditions
1 Principle-in-Charge* $ 19,088
2 Project Executive* / Manager $ 38,851
3 Project Manager* MEP $ 28,543
4 Superintendent* $ 19,240
5 Assistant Superintendent* N/A $ 0
6 MEPS Superintendent* Fulltime $ 58,872
7 Project Estimator* $ Included
th
135 W 50 Street Construction Manager RFP | PAGE 14