Proposed Fees, Costs, and Markups:



                Item     Phase                                                              Proposed Fee
                No.


                1        Pre-construction services (flat fee for 2                          $
                         months)                                                               15,000
                2        General conditions ( estimated  for 5                              $
                         months)                                                                219,581


                         Total                                                              $


                         CM fee as a percentage markup of                                                 %
                         direct costs, plus approved general                                   2.5
                         conditions
                         Insurance percentage markup of direct                                            %
                         costs, plus approved general conditions                                1.5
      Barr and Barr will return 100% of any savings realized in the G.M.P. 100% total transparency in

                      reporting and billing
      financial

             Construction Budget
               This solicitation should be based on a projected total hard cost construction budget range of
               $3,000,000.00 to $4,000,000.00.



             General Conditions
             Indicate below whether the following items are included or excluded in the general conditions
             proposed above in Item #2.  In order to minimize turnaround time and to facilitate an equal
             comparison of proposals, please do not deviate from the requested format.





                Item    Item                                  Included in     Excluded from    Total Cost
                No.                                             General           General
                                                               Conditions       Conditions
                1       Principle-in-Charge*                                                   $ 19,088
                2       Project Executive* / Manager                                           $ 38,851
                3       Project Manager*    MEP                                                $   28,543
                4       Superintendent*                                                        $   19,240
                5       Assistant Superintendent*              N/A                             $    0
                6       MEPS Superintendent*  Fulltime                                         $    58,872
                7       Project Estimator*                                                     $    Included





                                                                     th
                                                            135 W 50  Street Construction Manager RFP | PAGE 14