Page 12 - KUH Refresh Proposal 8.14.17
P. 12

Staffing Proposal

            Phase 1 - Garage

           1. Assumed Construction Duration: 13 months; Jan 1, 2018 – Feb 1, 2019
           2. For purposes of this RFP provide your staffing levels and billing rates for the project that will correlate with the General Conditions
           estimate in your GMP summary sheet.  List  the billing rate for each position to be charged to the project. All billing rates must be
           inclusive of the following: Base Salary, Bonus, PTO, Automobile and company vehicle costs, FICA (Social Security and Medicare
           Tax), Pension, Profit Sharing & Defined Contribution Plan, Medical, Dental, Vision, Life and Disability Insurance Plans, SUTA, FUTA
           Computer Equipment (Hardware & Software including project management software) Education (Internal and External),
           Parking/Transportation cost for employee parking and transportation to project sites, Mobile phone, & Workers Comp.  The rates
           stated must hold for the planned duration of the respective construction phase.
           3. For the OCIP option please provide the deduct amounts for xxx


           4. Provide a corresponding organizational chart that shows all the individuals proposed for the project.




                                                                                                       OCIP Billing
                                             Duration                           Billing rate
                    Position       Hours/Wk                     Name                          Total    rate deduct
                                              (weeks)                            ($/HR)
                                                                                                         ($/HR)
           Officer In Charge          8         56           Keith Stanisce                  No Charge
           Project Executive
           Sr Project Manager         4         56            John Duncan       $       170.86   $                   38,272.64   $7.64
           Project Manager Arch       32        56            Greg Ondick       $       123.04   $                 220,487.68   $5.43
           Project Manager MEP        16        56           Brooke Rogers      $       121.45   $                 108,819.20   $5.23
           Asst Project Manager Arch                                                      $                                -
           Asst Project Manager MEP                                                       $                                -
           Administrative Assistant   4         56          Rosemarie D'Elia    $         82.33   $                   18,441.92   $3.50
           Project Accountant         8         56           Gina Gagliardi     $         80.90   $                   36,243.20   $3.02
           Project Safety Manager     24        56           Reggie Shubert     $       124.97   $                 167,959.68   $5.21
           Superintendent             40        56           Russ Pembroke      $       149.14   $                 334,073.60   $4.97
           Superintendent             16        56           Mark Madjeski      $         77.44   $                   69,386.24   $3.32
           Assistant Superintendent   40        56           Victor Casilla     $         43.56   $                   97,574.40   $1.92
           Clerk of the Works         24        56           Wanda Shufford     $         70.37   $                   94,577.28   $2.46
           QA/QC Rep                  8         56            Greg Ondick       $       123.04   $                   55,121.92   $5.42
           Scheduler                  4         56             Abhi Basu        $       105.75   $                   23,688.00   $4.35
           Estimator                                                                      $                                -
                                                                                 Total    $              1,264,645.76


           Name:  Keith Stanisce

           Signature:

           Firm:  Barr & Barr, Inc.
           Date:  August 14, 2017