Staffing Proposal
Phase 1A - Preconstruction Services
1. Assumed Duration: 4 months; Sept 1, 2017 – Dec 31, 2017
2. For purposes of this RFP provide your staffing levels and billing rates for the project that will correlate with the General Conditions
estimate in your GMP summary sheet. List the billing rate for each position to be charged to the project. All billing rates must be
inclusive of the following: Base Salary, Bonus, PTO, Automobile and company vehicle costs, FICA (Social Security and Medicare
Tax), Pension, Profit Sharing & Defined Contribution Plan, Medical, Dental, Vision, Life and Disability Insurance Plans, SUTA, FUTA
Computer Equipment (Hardware & Software including project management software) Education (Internal and External),
Parking/Transportation cost for employee parking and transportation to project sites, Mobile phone, & Workers Comp. The rates
stated must hold for the planned duration of the phase.
3. For the OCIP option please provide the deduct amounts for xxx
4. Provide a corresponding organizational chart that shows all the individuals proposed for the project.
OCIP Billing
Duration Billing rate
Position Hours/Wk Name Total rate deduct
(weeks) ($/HR)
($/HR)
Officer In Charge 4 17 Keith Stanisce No Charge
Project Executive
Sr Project Manager 4 17 John Duncan No Charge
Project Manager Arch 8 17 Greg Ondick $ 46.40 $ 6,310.40 $1.90
Project Manager MEP 6 17 Brooke Rodgers $ 46.00 $ 4,692.00 $1.84
Asst Project Manager Arch 12 17 Chris Dantz $ 37.50 $ 7,650.00 $2.15
Asst Project Manager MEP $ -
Administrative Assistant $ -
Project Accountant 4 9 Gina Gagliardi $ 30.40 $ 1,094.40 $1.08
Project Safety Manager $ -
Superintendent 8 17 Russ Pembroke $ 57.20 $ 7,779.20 $1.77
Superintendent $ -
Assistant Superintendent $ -
Clerk of the Works $ -
QA/QC Rep $ -
Scheduler 2 17 Abhi Basu $ 40.00 $ 1,360.00 $1.60
Estimator 16 17 Mutiple $ 34.00 $ 9,248.00 $1.48
Total $ 38,134.00
Name: Keith Stanisce
Signature:
Firm: Barr & Barr, Inc.
Date: August 14, 2017