Thomas J. LePage
                                                       Project Executive


         EDUCATION
         Pratt Institute of Technology
         B.P.S. Construction Management
         American Society for Healthcare Engineering
         (ASHE)
         Construction Certifi cate

         SPECIAL TRAINING
         NYC Licensed Site Safety Manager

         YEARS OF EXPERIENCE
         36
         YEARS WITH BARR & BARR
         28



        As Project Executive, Tom will oversee your project from the corporate level and have full contractual authority.  In his 36
        years of experience, his attentional to detail and team leaderhsip is second to none.  He will work closely with the project
        team ensuring that the project stay both on schedule and within budget.  Tom’s experience within the industry assures both
        quality and successful financial project completion.

        SIMILAR PROJECTS

        Cornell NYC Tech, The Bloomberg Center,                Robert Wood Johnson University Hospital,
                                                               New Brunswick, NJ
        Roosevelt Island, NY                                   252,000 SF (650+ spaces), 56,000 SF (Offi  ce Space). Th e project
        150,000 SF. Th  e Bloomberg Center is the fi rst of several buildings to   includes a nine-story garage capable of holding 650+ cars and a
        be constructed of the new Cornell NYC Tech Campus on Roosevelt   new service vault with new substation and generators. On top of
        Island.  Th  e Bloomberg Center provides graduate students, faculty
        and administrators with a new facility for research and education.  Th e   the garage will be two stories of offi  ce space and a data center. Th e
        building design refl ects Cornell’s goals of creativity and excellence,   structure and building systems are designed for additional vertical
        providing fl exible academic spaces and pioneering new standards   expansion in the future.
        in building performances and sustainability.
                                                               Dollar Value: $70 Million
                                                               Start Date: March 2013
        Dollar Value: $130 Million
        Start Date: December 2014                              Completion Date: February 2016
        Completion Date: May 2017
                                                               South Nassau Communities Hospital,
        Rutgers University, Chemistry and Chemical Biology Building,
        New Brunswick,NJ                                       Oceanside, NY
        145,000 SF. Th  is new four story  (above grade) Chemistry and   14,000 SF. Th  e South Nassau Communities Hospital Emergency
        Chemical Biology, with a basement and penthouse, will house   Department is expanding. Th  is is southern Nassau County’s only
        classrooms, administration offi  ces, research laboratories and a 120   Trauma Level II Center. Looking to continue their state-of-the-art
        seat auditorium.  Th  e lobby doubles as a presentation and gathering   emergency care to the residents of the South Shore, this project will
                                                               increase the Emergency Department’s square footage from 16,000
        space and the  basement includes specialty imaging facilities.   to 30,000 square feet. Th  is will give them the necessary room to
                                                               accommodate a projected 70,000 patient visits each year as well
        Dollar Value: $103 Million                             as establish dedicated areas for behavioral health and pediatric
        Start Date: June 2014                                  emergencies.
        Completion Date: September 2017
                                                               Dollar Value: $13.2 Million
        Northern Westchester Hospital Services, Mount Kisco, NY  Start Date: November 2016
        18,000 SF.  Th  e Surgical Services Project expanded the existing  Completion Date: May 2017
        surgical suite by 18,000 s.f.  adding six new OR’s and 14 PACU
        stations to their surgical suite.  Th  is project was built over the
        existing ED and required the structural reinforcing of existing
        facility to accommodate the new facility built on the former roof
        of the existing ED.

        Dollar Value: $23.5 Million
        Start Date: March 2013
        Completion Date: January 2016