Plumbing, HVAC, Central Utility Plant

                                               UMC of Princeton – Plainsboro, NJ




























         References:                                               EPC Contractor’s Role:
         Concord Engineering Group, Inc.                           Installer only
         Guy Molinari
         856-427-0200                                              Construction Dates:
                                                                   Construction: 2/2011 - 9/2011
         Project Description:
         Privately Funded. Late design changes made it necessary to incorporate a  Current Operating Status:
         CHP addition to the plant. Th  e schedule demands of the plant required  Currently operational
         the chilled water plant to be brought on line in approximately 8 weeks
         after release of the slab-on-grade and the high pressure steam plant 11  Description of Claims:
         weeks after slab-on-grade. Based on the size and complexity of this  None
         20,000 sq ft plant, these were very aggressive durations.
         Fortunately, both timelines were met largely due to detailed planning
         and extensive prefabrication. Th  e entire building was designed using
         BIM, state-of-the-art 3D modeling, which provided project requirements
         specifi c to each inline component and the equipment necessary to connect
         it. Th  is level of design made it possible to prefabricate all the pumps
         and large bore piping off -site, preassemble whenever possible and load
         on skids ready for delivery – all ahead of the slab completion. Binsky
         also worked alongside the engineer to review the model throughout the
         design process and resolved a large percentage of constructability issues
         before the fi rst piece of pipe arrived on site.
         Th  is CUP will suffi  ciently power the new 636,000 sq foot facility when
         completed.

         Construction Cost:
         $3.3 Million

         Project Schedule:
         7 months – schedule met