Page 30 - Barr&Barr_Trinitas RFQ No. CHP-2010_Flipbook
P. 30
Combined Heating Cooling and Power Plant
Montclair Central Energy Center - Little Falls, NJ
References: EPC Contractor’s Role:
DCO Energy Installer only
Dennis Fischer
(609) 512-2245 Construction Dates:
Design and construction activities were coordinated to maintain
Project Description: steam and electrical services to the campus buildings throughout
Privately Funded. Th e Combined Heating Cooling and Power the construction period.
(CHCP) plant includes a combustion turbine generator, a heat
recovery steam generator (HRSG) with duct fi ring, an auxiliary Current Operating Status:
steam boiler, chillers, cooling towers and electrical generation Operational
equipment.
Description of Claims:
Th e plant contains electric generation via a gas turbine generator, None
chilled water, cooling water, auxiliary cooling water, steam
production equipment, primary pumping systems, high voltage
electrical distribution, and fuel storage required to support the
combustion gas turbine and the auxiliary boiler.
Construction Cost:
$5 Million
Project Schedule:
Project met delivery schedule.