Page 25 - Barr&Barr_Trinitas RFQ No. CHP-2010_Flipbook
P. 25

Homewood Campus Combined Heat and Power Plant

                                            John Hopkins University– Baltimore, MD




























         References:                                               EPC Contractor’s Role:
         David Ashwood, Director of Plant Operations               Th  e design included a 8,150 square foot addition to the
         Johns Hopkins University                                  existing power plant to house the new CHP system. Since the
         P: (410) 516-8060                                         existing power plant is centrally located on the University’s
         E: dashwood@jhu.edu                                       campus, the design for the addition included sound attenuation
                                                                   strategies to avoid disruption to the campus activities while
         Project Description:                                      supporting continuous operation of the CHP system. Th e
         Started as design/bid/build and switched to design assist. Funded by  design included pre-purchasing of all major equipment for
         Johns Hopkins. Th  e cogeneration system consists of a nominal 4.6 MW  the project, including procurement of the Solar Centaur 50
         combustion turbine and a heat recovery steam generator (HRSG). Th is  turbine. To fully utilize CHP’s electric and steam output,
         CHP is operated as a base load unit generating 4.6 MW of electric  modifi cations were made to the campus’ 13.2 kV electric
         power at 13.2 kV and 25,000 PPH steam at 125 PSI. Th e steam output  distribution system to shift campus electric loads to the
         is connected to the existing campus steam distribution system to  CHP system. To fully utilize steam loads during summer, a
         supplement existing boiler steam generation to serve the campus heating  large electric driven condenser water pump used for campus
         loads. Th  e electric output operates in parallel to the incoming electric  cooling was changed over to a steam-driven unit.
         utility to reduce overall energy demands from the campus’ electrical
         distribution system.                                      Construction Dates:
                                                                   Professional Services: 06/2008-07/2009
         Th  e design included a 8,150 square foot addition to the existing power  Construction: 10/2010 - 07/2011
         plant to house the new CHP system. Since the existing power plant is  Date of operation: 07/2011
         centrally located on the University’s campus, the design for the addition
         included sound attenuation strategies to avoid disruption to the campus  Current Operating Status:
         activities while supporting continuous operation of the CHP system.  Each year AEI provides a detailed review and audit of the
                                                                   performance of the system. To date the systems have met
         Construction Cost:                                        or exceeded operating savings.
         $7.4 Million
                                                                   Description of Claims:
         Project Schedule:                                         None
         Th  is project, successfully completed in June 2011 at a construction cost
         of $7.4 million, resulted in operational cost savings of approximately
         $1.5 million per year and is reducing greenhouse gas emissions by 9,500
         metric tons of carbon dioxide equivalent per year. project was delivered
         on time.  Client felt that cooperative nature of Cx and start up services
         provided eliminated 2 months from the schedule.
   20   21   22   23   24   25   26   27   28   29   30