Page 24 - Barr&Barr_Trinitas RFQ No. CHP-2010_Flipbook
P. 24

Energy Plants

                                          John Hopkins Health Institutions - Baltimore, MD




























           References:                                            Project Schedule:
           David Eldridge, Plant Manager                          Project was able to meet aggressive schedule and was delivered.
           Th  e Johns Hopkins Health System                      on time.
           P: (410) 955-5278
           E: deldridge@jhmi.edu                                  EPC Contractor’s Role:
                                                                  AEI provided comprehensive commissioning, training and start-
           Project Description:                                   up services for the installation. Th  e unique AEI start-up services
           Project started as traditional design/bid/build and switched to   assist the contractor and owner with component interfaces such
           design assist. Funded by Johns Hopkins. Th  e Johns Hopkins   as controls, point-to-point wiring, etc. Johns Hopkins has stated
           Health Institutions are served by two interconnected energy plants   that AEI start-up services reduced the time period for benefi cial
           that were planned, designed and commissioned by Affi  liated   operation by three months.
           Engineers (AEI). For over 30 years, AEI has provided continuous
           engineering services in support of the most signifi cant infrastructure   Construction Dates:
           modernization projects constructed at the Johns Hopkins’ campus.   Professional Services: 01/2001-01/2010
                                                                  Construction: 06/2011 - 8/2012
           North Energy Plant (Total Plant Generation Capacities)  Date of operation: 8/2012
           30,500 Tons of Refrigeration
           475,000 PPH of Steam                                   Current Operating Status:
           7.5 MW of CHP                                          Each year AEI provides a detailed review and audit of the
           6.0 MW of Centralized Emergency, Stand-by Power        performance of the systems. Since initial operation, the systems
                                                                  have met or exceeded operating savings.
           South Energy Plant (Total Plant Generation Capacities)
           21,000 Tons of Refrigeration                           Description of Claims:
           115,000 PPH of Steam                                   None
           7.5 MW of CHP
           12.0 MW of Centralized Emergency, Stand-by Power

           Construction Cost:
           $35 Million (for both Plants)
   19   20   21   22   23   24   25   26   27   28   29