Page 28 - Barr&Barr_Trinitas RFQ No. CHP-2010_Flipbook
P. 28

Houston Methodist Hospital

                                             Central Utility Plant Upgrade - Houston, TX




























           References:                                            With very limited space in and around the existing equipment,
           Kyle Roth, Senior Project Director, Facilities & Construction  the upgrades were confi gured with the cogeneration unit being
           Th  e Woodlands Hospital                               located on the roof. Th  e chiller replacement, as well as the chilled
           P: (713)-441-1325                                      water and condenser water system header modifi cations, occurred
           E: ckroth@houstonmethodist.org                         on the main level of the plant. Th  e new pumps were located on
                                                                  the lower level of the plant.
           Project Description:
           Traditional design/bid/build. Funded by Houston Methodist   Construction Dates:
           Hospital. AEI led the project team that included mechanical,   Professional Services: 9/2007-7/2008
           electrical, and piping/plumbing engineering, architectural, civil,   Construction: 06/2009 - 12/2010
           and structural design services to increase the central utility plant   Included much of the hospital construction schedule as well.
           steam system capacity from 120,000 pounds per hour to 170,000   Date of operation: 12/2010
           pounds per hour and chilled water production capacity from
           10,000 tons to 14,800 tons.                            Current Operating Status:
                                                                  Operational
           Construction Cost:
           $25.1 Million                                          Description of Claims:
                                                                  None
           Project Schedule:
           Project met delivery schedule.


           EPC Contractor’s Role:
           Pump pipe cross-connectivity reliability concerns were addressed
           by the installation of motorized isolation valves in the chilled water
           and condensed water piping.  Additional piping cross connects
           and manual bypass/isolation valves were also included to allow
           dedicated chilled and condensed water pumps to cross connect
           to other nearby chillers. Variable frequency drives were added
           to the cooling tower fans, chilled water pumps, and condensed
           water pumps to provide greater control of the chilled water and
           condenser water pumping systems. By adding additional cooling
           tower capacity and manual valves/bypass connections, a higher
           level of redundancy was achieved.
   23   24   25   26   27   28   29   30   31   32   33