Page 5 - BarrandBarr_Garage Portfolio.indd
P. 5

Williams College

                                                 Parking Garage and Chiller Plant


































          SIZE                     OWNER
          95,000 square feet (236 spaces)  Williams College

          CONTRACT TYPE            ARCHITECT
          Construction Manager-at-Risk  William Rawn Associates,
                                   Architects






                                                                       PROJECT DETAILS
         Th  e new three-deck parking structure consisted of precast columns and       •   Extensive site coordination because the parking
         deck and included new water lines, sewer lines, storm drainage, high   structure was carved into the hillside to allow
         voltage electrical lines, chilled water piping, data and communication lines   the top level to be at grade on the east side while
         as well as a new storm water retention basin. Th  e garage was designed to   the bottom level is at grade on the west side.
         accommodate campus expansion and houses a new central chiller plant
                                                                          •   Massive excavation and large foundations
         that services the ‘62 Center for Th  eatre & Dance.
                                                                           and retaining walls were required due to poor
                                                                           existing soil conditions.
                                                                          •   Astute planning enabled relocation of existing
                                                                           site utilities.