UMass Lowell

                                                  South Campus Parking Garage


































          SIZE                     OWNER
          226,025 square feet (762 spaces) UMass Lowell
                                   (UMBA project)
          CONTRACT TYPE
          Construction Manager-at-Risk  ARCHITECT
                                   Walker Parking Consultants







                                                                       PROJECT DETAILS
          Th  e South Campus Parking Garage features a fi ve-story precast concrete       •   UMass Building Authority (UMBA) funded
          open-air parking facility built on the existing Riverview surface parking   project.
          lot. Th  e structure accommodates 762 passenger vehicles and houses
                                                                          •   Astute planning for adjusted enabling
          equipment storage, mechanical space, stair and elevator towers, a glass-
                                                                            infrastructure and coordinated site access to
          enclosed lobby and a full security system featuring CCTV cameras,
                                                                            ensure timely construction sequencing.
          call assistance stations and vehicle and pedestrian card access systems.
                                                                          •   Investigation and hazardous materials survey
                                                                            to verify service locations and expose hidden
                                                                            subsurface/soil conditions.

                                                                          •   Extensive coordination with Massachusetts
                                                                           Bay Transit Authority (MBTA) due to location
                                                                           of adjacent and active railroad tracks.
                                                                          •   Implementation of several early design
                                                                           release packages to ensure procurement of
                                                                           long-lead items to meet overall project schedule
                                                                           constraints.