Page 24 - Property Rights in the Philippine A Time and Cost Study_July 2017
P. 24
Annex A Input - Process - Output Tables of the Five Major Processes in Issuance of the Residential Free Patent
Table 4. Input-Process-Output Table of Systematic Adjudication
INPUT PROCESS OUTPUT COST DURATION
SITE SELECTION
Actor
LGU and DENR
1 List of selection of priority Activities Selected barangay NA 5 days
barangay
Selects appropriate barangay
for Residential Free Patent
Titling base on the initial data on
zoning and lot status
PREPARATION OF ZOING
MAP
Actor
2 Selected barangay LGU Planning and Development Zoning Map of the adjudication NA 5 days
Officer
area
Activities
Prepares the Zoning Map for the
selected adjudication area
PREPARATION OF
BARANGAY LOT STATUS
3 Selected barangay Actor Barangay Lot Status NA 60 days
CENRO Records Officer
Activities
Prepares the Barangay Lot
Status
23