                           unchecked, the ceiling height and finish   •  Specify the Height Raised, which is the
                           material within the window is the same as   measured from the floor height of the
                           that for the adjacent room.             adjacent room.
                        •  Specify the Height Lowered, which is
                           measured from the ceiling height of the   Note: If the Height Raised is 0”, Has Raised
                           adjacent room.                        Floor will become unchecked when you click
                                                                 OK.

                         Note: If the Height Lowered is 0”, Has Low-  •  Check Use Floor Finish to measure the
                         ered  Ceiling  will  become  unchecked  when  Height Raised distance from the surface
                         you click OK.
                                                                   of the floor finish. When unchecked, as it
                        •  Specify the Finish Thickness, which is   is by default, this height is measured
                           the thickness of the ceiling’s finish mate-  from the subfloor.
                           rial.                                •  Specify the Finish Thickness, which is
                        •  Specify the Structure Thickness, which   the thickness of the floor’s finish mate-
                           is the thickness of the ceiling’s structural   rial.
                           layer.                               •  Specify the Structure Thickness, which
                                                                   is the thickness of the floor’s structural
                         5  Specify the height and structure of the   layer.
                            Floor within the selected window.
                        •  Check Has Raised Floor to enable the   6  Check Include in Schedule to include
                           settings that follow. When this is       the selected window(s) in Window
                           unchecked, the floor height and material   Schedules. See “The Schedule Tools” on
                           within the window is the same as that for   page 668.
                           the adjacent room.