Page 27 - August_10th_SrSteerCo_e_bookwof
P. 27
Project B Key Milestones
2017 2018
Month Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Activity Week of 06. 13. 20. 27. 03. 10. 17. 24. 01. 08. 15. 22. 29. 05. 12. 19. 26. 03. 10. 17. 24. 31. 07. 14. 21. 28. 04. 11. 18. 25. 04. 11. 18. 25. 01. 08. 15. 22. 29. 06. 13. 20. 27. 03. 10. 17. 24. 01. 08. 15. 22. 29. 05. 12. 19. 26. 02. 09. 16. 23. 30. 07. 14. 21.
Target Definition
Planning
Develop concept &
Implementation
rd
3 Steerco Meeting (Go/No-Go) 8/7
Sr. Executive Meeting (Go/No-Go) 8/10
Implementation Planning 8/14 – 8/17
Implementation of Project Bold
Design, programming & graphics
10/2/17 - 12/29/17
Logistics
10/2/17 - 3/30/18
Zine Team
10/2/17 - 12/29/17
Pre-fabrication
1/1/18 - 6/29/18
Digital Deployment
10/2/17 - 10/31/18
9/25/17
Roll out
Solutions
Go/No-go
Confidential© Siemens AG 2017 Phase Activity Milestone
Page 27 08/07/2017 Names are for example only Siemens Industry, Inc.