Decisions for Steering Committee
Decision I:
Approval on structure of the Zone Technical Center along with the approval to analyse headcount to
staff the Zone Technical Center
Decision II:
Approval to request proposals for licensing of technology for the Zone Technical Center- such as
WRIKE, Blue Beam, Logistics Platform, IT/SAP
Decision III:
Approval to continue to develop Field Logistics Plan and Warehouse Network
Decision IV:
Approval of project timeline