Decisions for Steering Committee









               Decision I:
               Approval on structure of the Zone Technical Center along with the approval to analyse headcount to
               staff the Zone Technical Center




               Decision II:
               Approval to request proposals for licensing of technology for the Zone Technical Center- such as
               WRIKE, Blue Beam, Logistics Platform, IT/SAP






               Decision III:
               Approval to continue to develop Field Logistics Plan and Warehouse Network








               Decision IV:
               Approval of project timeline