Page 604 - Facilities Master Plan 2016
P. 604

Lodi Unified School District                                            Lodi Unified School District
          Beckman Elementary School                                               Beckman Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                     19-Apr-16  Opinion of Probable Cost                                    19-Apr-16
                          Project Cost Summary (2016$) - Beckman Elementary School               Project Cost Summary (2016$) - Beckman Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                       Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
            4b New Construction - Classrooms
            4b.1 Remove Portable Classrooms                        3 ea  $       11,000.00  11 Library & Student Support Services  $                       -  $                             -
            4b.2 Relocate Portable Classrooms                        2 ea  $       25,000.00  11a Elementary School Library/Innovation Lab
            4b.3 Demolish Existing Buildings                   865 sf  $               22.00  11a.4 Reconfigure Library/Innovation Lab Building                3,900 sf  $             244.00
                                                                                   11d Learning Center
            4b.5 New Elementary Classroom Building (2-story)             12,768 sf  $             449.00  11d.3 Modernize Learning Center                   704 sf  $             119.00
            4b.10 Sitework & Site Improvements                6,384 sf  $               38.00  11d.4 Reconfigure Learning Center                   960 sf  $             237.00
            4d Student Collaboration Lab
            4d.1 New Student Collaboration Lab, 2 - Story                1,915 sf  $             426.60
            4d.2 Sitework & Site Improvements                   958 sf  $               38.00  12 Safety, Security & Campus Control  $           1,523,000 $                 2,026,000
                                                                                   12b Safety improvements to and/or new parent/bus drop-off areas and parking
                                                                                    12b.1 New Parking Lot              20,625 sf  $               16.00 $            330,000
          05 Maker Spaces & Science Labs                   $                       -  $                             -  12b.3 Entry Plaza                2,100 sf  $               26.00
            5a ES Science / Creativity Labs                                         12b.5 New Drop-off Area             10,350 sf  $               18.00 $            186,000
            5a.6 New ES Science / Creativity Labs Building                 3,724 sf  $             475.20  2-story  12b.9 Repair existing Parking Lot             29,725 sf  $                 6.30 $            187,000
            5a.7 Sitework & Site Improvements                1,862 sf  $               38.00  12b.11 New concrete walkways                4,250 sf  $               15.00 $              64,000
                                                                                   12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000
                                                                                   12e Safety locks at classroom doors                     40 ea  $             449.00 $              18,000
          06 Electives                                     $                       -  $                             -  12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
            Not included in this Facilities Needs Assessment                       12g Marquee Sign                               1 ea  $       10,000.00 $              10,000
                                                                                   12h Fencing with controlled campus entrances
                                                                                    12h.2 Decorative Metal Fencing & Gates                   375 lf  $             252.00 $              95,000
          07 Performing Arts Improvements                  $                       -  $                             -  12i Fire safety equipment, fire alarms and emergency lighting
            7a Music Lab                                                            12i.1 Fire Alarm System             34,664 sf  $                 5.40 $            187,000
            7a.4 New Music Lab                     1,862 sf  $             484.92  2-story  12i.2 Emergency Lighting             34,664 sf  $                 1.40 $              49,000
            7a.5 Sitework & Site Improvements                   931 sf  $               38.00  12j New public address/emergency communication
                                                                                   systems                             34,664 sf  $                 7.60 $            263,000
                                                                                   12k Intrusion alarms                34,664 sf  $                 1.80 $              62,000
          08 Multi-Purpose Room / Food Service Improvements & Student Dining  $                       -  $                             -
            8a Elementary/Middle School multipurpose rooms
            8a.2 Modernize Multipurpose Room                4,608 sf  $               99.00  13 District Support Facilities       $                       -  $                             -
            8c Food service areas                                                  Not included in this Facilities Needs Assessment
            8c.2 Modernize Food Service                   840 sf  $             175.00
            8c.6 New Trash Enclosure                        1 ea  $       45,000.00
            8d New Lunch Shelters                  2,400 sf  $               72.00  14 Outdoor Learning Environments & Quads      $                       -  $                             -
                                                                                   14a Main Student Quad
                                                                                    14a.2 New Main Student Quad                9,800 sf  $               19.55
          09 Physical Education Improvements               $                       -  $                             -  14b Learning Courts
            9c PE/Fitness Labs                                                      14b.2 New Learning Court                3,300 sf  $               23.00
            9c.4 New PE/Fitness Labs                2,554 sf  $             436.32  2-story
            9c.5 Sitework & Site Improvements                1,277 sf  $               38.00
                                                                                  15 Exterior Play Spaces, Playfields & Hardcourts  $                       -  $                             -
                                                                                   15a Kindergarten Play Yard
          10 Administration & Staff Support                $                       -  $                             -  15a.1 New Rubberized Surface Play Area                1,500 sf  $               20.00
            10a Expanded, reorganized or relocated administration                   15a.3 Shade Structure                 1,200 sf  $               90.00
            spaces                                                                  15a.6 New Hardcourts                  5,450 sf  $               11.00
            10a.3 Reconfigure Administration                1,608 sf  $             235.00  15a.7 Slurry Coat & Stripe Existing Hardcourts                4,800 sf  $                 3.00
            10b Staff Collaboration/Work Rooms                                     15b PE Play Yard & Hardcourts
            10b.2 Modernize Staff Collaboration/Work Rooms                   288 sf  $             118.00  15a.1 New Rubberized Surface Play Area                5,200 sf  $               20.00
            10b.3 Reconfigure Staff Collaboration/Work Rooms                   480 sf  $             235.00  15b.7 Slurry Coat & Stripe Existing Hardcourts             64,100 sf  $                 3.00
            10b.4 New Staff Collaboration/Work Rooms                   638 sf  $             423.36  2-story  15b.8 Basketball Court/Sports Equipment                        1 ls  $       25,333.33
            10b.5 Sitework & Site Improvements                   319 sf  $               38.00  15c Playfields
                                                                                    15c.1 Repair Playfields             92,350 sf  $                 3.00
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.3       APPENDIX                                                                                                    Facilities Master Plan  575
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District