Lodi Unified School District                                            Lodi Unified School District
          Lois E. Borchardt Elementary School                                     Lois E. Borchardt Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                       Project Cost Summary (2016$) - Lois E. Borchardt Elementary School      Project Cost Summary (2016$) - Lois E. Borchardt Elementary School
                                                       Construction Costs   Total Project                                      Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          08 Multi-Purpose Room / Food Service Improvements & Student Dining  $                       -  $                             -  14 Outdoor Learning Environments & Quads  $                       -  $                             -
            8a Elementary/Middle School multipurpose rooms                         14b Learning Courts
            8a.3 Reconfigure Multipurpose Room                   800 sf  $             296.00  stage  14b.2 New Learning Court                4,000 sf  $               23.00
            8d New Lunch Shelters                 2,400 sf  $               72.00
                                                                                  15 Exterior Play Spaces, Playfields & Hardcourts  $                       -  $                             -
          09 Physical Education Improvements               $                       -  $                             -  15a Kindergarten Play Yard
            9c PE/Fitness Labs                                                      15a.1 New Rubberized Surface Play Area                4,000 sf  $               20.00
            9c.4 New PE/Fitness Labs                2,112 sf  $             404.00  15a.2 Kindergarten Play Apparatus                        1 ea  $       63,000.00
            9c.5 Sitework & Site Improvements                2,112 sf  $               38.00  15a.3 Shade Structure                1,200 sf  $               90.00
                                                                                    15a.6 New Hardcourts                  9,600 sf  $               11.00
                                                                                   15b PE Play Yard & Hardcourts
          10 Administration & Staff Support                $                       -  $                             -  15a.1 New Rubberized Surface Play Area                6,000 sf  $               20.00
            10a Expanded, reorganized or relocated administration                   15b.2 Elementary Play Apparatus                        1 ea  $       63,000.00
            spaces                                                                  15b.6 New Hardcourts               37,800 sf  $               11.00
            10a.3 Reconfigure Administration                   750 sf  $             235.00  15b.8 Basketball Court/Sports Equipment                        1 ls  $       25,333.33
          11 Library & Student Support Services            $                       -  $                             -  16 Next Generation Classroom Flexibility (Furniture)  $                       -  $                             -
            11a Elementary School Library/Innovation Lab                           16a Flexible furniture (Per Classroom, Direct Cost)                     32 ea  $         7,500.00
            11a.2 New Library/Innovation Lab Building                1,320 sf  $             406.00
            11a.5 Sitework & Site Improvements                1,320 sf  $               38.00
            11d Learning Center                                                   17 Technology Infrastructure                    $                       -  $                             -
            11d.4 Reconfigure Learning Center                1,950 sf  $             237.00  Not included in this Facilities Needs Assessment
                                    .
          12 Safety, Security & Campus Control             $              837,000 $                 1,113,000  Total Construction/Project Cost (2016$)  $              837,000  $1,113,000
            12b Safety improvements to and/or new parent/bus drop-off areas and parking
            12b.1 New Parking Lot              16,800 sf  $               16.00 $            269,000
            12b.5 New Drop-off Area             10,800 sf  $               18.00 $            194,000  The following items are excluded from this budget:
            12b.11 New concrete walkways                2,400 sf  $               15.00 $              36,000  Utility hook-up fees & City connection fees.
            12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000  Offsite work and traffic signals.
            12e Safety locks at classroom doors                     45 ea  $             449.00 $              20,000  Land acquisition costs.
            12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000  Hazardous material surveys, abatement, and disposal.
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000  Escalation (Costs are in 2016$ calculated to the end of the year).
            12h Fencing with controlled campus entrances
            12h.2 Decorative Metal Fencing & Gates                   830 lf  $             252.00 $            209,000
            12h.3 Rolling Decorative Metal Gate                        1 ea  $       27,000.00 $              27,000
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System                2,700 sf  $                 5.40
            12i.2 Emergency Lighting                2,700 sf  $                 1.40
            12j New public address/emergency communication
            systems                               2,700 sf  $                 7.60
            12k Intrusion alarms                  2,700 sf  $                 1.80
          13 District Support Facilities                   $                       -  $                             -
            Not included in this Facilities Needs Assessment




         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  577
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District
   601   602   603   604   605   606   607   608   609   610   611