Lodi Unified School District                                            Lodi Unified School District
          Clairmont Elementary School                                             Clairmont Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                   19-Apr-16
                         Project Cost Summary (2016$) - Clairmont Elementary School              Project Cost Summary (2016$) - Clairmont Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
                                                                                   4b New Construction - Classrooms
          01 Modernize & Reconfigure Aging Classrooms      $                       -  $                             -  4b.1 Remove Portable Classrooms                        5 ea  $       11,000.00 $              55,000
            1b Replacement or repair of walls                                       4b.2 Relocate Portable Classrooms                        4 ea  $       25,000.00 $            100,000
            1b.2 Repair walls                  14,580 sf  $               12.60
            1c Replacement or repair of windows                                     4b.4 New Elementary Classroom Building (1-story)                4,224 sf  $             404.00 $         1,706,000
            1c.2 Repair windows                14,580 sf  $                 3.60    4b.10 Sitework & Site Improvements                4,224 sf  $               38.00 $            161,000
            1d Replacement or repair of doors (other than safety locks             4d Student Collaboration Lab
            @ classroom doors)                                                      4d.1 New Student Collaboration Lab, 1- Story                1,056 sf  $             395.00 $            417,000
            1d.2 Repair doors & hardware             14,580 sf  $                 4.50  4d.2 Sitework & Site Improvements                1,056 sf  $               38.00 $              40,000
            1e Replacement or repair of floors
            1e.1 Replace floors                14,580 sf  $               14.40
            1f Replacement or repair of ceilings                                  05 Maker Spaces & Science Labs                  $                       -  $                             -
            1f.1 Replace ceilings              14,580 sf  $               27.00    5a ES Science / Creativity Labs
            1g Patch & Paint Interior/Exterior                                      5a.6 New ES Science / Creativity Labs Building                 3,080 sf  $             440.00
            1g.1 Patch & paint interior             14,580 sf  $                 3.10  5a.7 Sitework & Site Improvements                3,080 sf  $               38.00
            1g.2 Patch & paint exterior             14,580 sf  $                 4.50
            1n Repair Existing Roofing             28,680 sf  $               14.00
                                                                                  06 Electives                                    $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
          02 Existing Building Systems & Toilets           $                       -  $                             -
            2a HVAC system upgrades             14,580 sf  $               29.00
                                                                                  07 Performing Arts Improvements                 $                       -  $                             -
            2b Lighting upgrades - new interior lighting & controls             14,580 sf  $               15.00  7a Music Lab
            2c Electrical upgrades                                                  7a.4 New Music Lab                    1,540 sf  $             449.00
            2c.1 Upgrade electrical wiring & increase electrical                    7a.5 Sitework & Site Improvements                1,540 sf  $               38.00
            outlets                            14,580 sf  $                 9.00
            2d Plumbing system upgrades             14,580 sf  $               11.00
            2e Replace aging plumbing, upgrade and/or expand                      08 Multi-Purpose Room / Food Service Improvements & Student Dining  $              988,000 $                 1,314,000
            restroom facilities                                                    8a Elementary/Middle School multipurpose rooms                P3
            2e.1 Modernize Existing Restroom                   750 sf  $               83.00  8a.2 Modernize Multipurpose Room                3,250 sf  $               99.00 $            322,000
            2e.3 New Restroom                        750 sf  $             556.00   8a.4 New Multipurpose Room                1,250 sf  $             494.00 $            618,000
            2e.4 Sitework & Site Improvements                   750 sf  $               57.00  8a.5 Sitework & Site Improvements                1,250 sf  $               38.00 $              48,000
            2f Energy-efficient building systems and controls (EMS                 8c Food service areas
            system, per sf of Bldg)             14,580 sf  $                 7.20
                                                                                    8c.2 Modernize Food Service                   800 sf  $             175.00
                                                                                    8c.6 New Trash Enclosure                        1 ea  $       45,000.00
          03 Site Utilities                                $                       -  $                             -
            (For entire campus and site)                                          09 Physical Education Improvements              $                       -  $                             -
            3a Updated gas service lines           392,040 sf  $                 0.14  9c PE/Fitness Labs
            3b Updated sewer service lines           392,040 sf  $                 0.25
            3c Updated water service lines           392,040 sf  $                 0.32  9c.4 New PE/Fitness Labs                2,112 sf  $             404.00
                                                                                                                    $
                                                                                                                        38.00

                                                                                    9c.5 Sitework & Site Improvements
                                                                                                              2,112 sf
            3d Updated electrical mains and distribution           392,040 sf  $                 0.72
            3f Electrical Capacity Upgrades                        1 ls  $     115,000.00
                                                                                  10 Administration & Staff Support               $                       -  $                             -
                                                                                   10a Expanded, reorganized or relocated administration
          04 Classrooms New Construction                   $           3,122,000 $                 4,152,000  spaces
                                                                                    10a.2 Modernize Administration                2,900 sf  $             118.00
            4a New Construction - Pre-School, DK & Kindergarten  (1) K & (4) CR's  P2
                                                                                   10b Staff Collaboration/Work Rooms
                                                                                    10b.2 Modernize Staff Collaboration/Work Rooms                1,100 sf  $             118.00
            4a.2 New Pre-School, DK & Kindergarten Building                1,485 sf  $             395.00 $            587,000
            4a.4 Sitework & Site Improvements                1,485 sf  $               38.00 $              56,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.3       APPENDIX                                                                                                    Facilities Master Plan  578
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District
   602   603   604   605   606   607   608   609   610   611   612