Page 612 - Facilities Master Plan 2016
P. 612
Lodi Unified School District Lodi Unified School District
Davis Elementary School Davis Elementary School
Facilities Master Plan - Total Program Cost Facilities Master Plan - Total Program Cost
Opinion of Probable Cost 19-Apr-16 Opinion of Probable Cost 19-Apr-16
Project Cost Summary (2016$) - Davis Elementary School Project Cost Summary (2016$) - Davis Elementary School
Construction Costs Total Project Construction Costs Total Project
Item Quantity Unit Unit Cost Subtotal Total Cost 25% (x 1.33) Item Quantity Unit Unit Cost Subtotal Total Cost 25% (x 1.33)
15c Playfields
11 Library & Student Support Services $ - $ - 15c.1 Repair Playfields 172,950 sf $ 3.00
11a Elementary School Library/Innovation Lab
11a.2 New Library/Innovation Lab Building 4,290 sf $ 406.00
11a.5 Sitework & Site Improvements 4,290 sf $ 38.00 16 Next Generation Classroom Flexibility (Furniture) $ - $ -
11d Learning Center 16a Flexible furniture (Per Classroom, Direct Cost) 16 ea $ 15,000.00
11d.4 Reconfigure Learning Center 1,920 sf $ 237.00
17 Technology Infrastructure $ - $ -
12 Safety, Security & Campus Control $ 1,200,000 $ 1,596,000 Not included in this Facilities Needs Assessment
12a Remaining asbestos removal 19,815 sf $ 4.00 $ 79,000
12b Safety improvements to and/or new parent/bus drop-off areas and parking
12b.1 New Parking Lot 9,600 sf $ 16.00 $ 154,000 Total Construction/Project Cost (2016$) $ 6,878,000 $9,147,000
12b.3 Entry Plaza 5,000 sf $ 26.00
12b.9 Repair existing Parking Lot 50,300 sf $ 6.30 $ 317,000
12b.11 New concrete walkways 2,200 sf $ 15.00 $ 33,000 The following items are excluded from this budget:
12d Exterior lighting to ensure student safety 1 ls $ 40,000.00 $ 40,000 Utility hook-up fees & City connection fees.
12e Safety locks at classroom doors 25 ea $ 449.00 $ 11,000 Offsite work and traffic signals.
12f Signage for emergency response and wayfinding 1 ls $ 32,000.00 $ 32,000 Land acquisition costs.
12g Marquee Sign 1 ea $ 10,000.00 $ 10,000 Hazardous material surveys, abatement, and disposal.
12h Fencing with controlled campus entrances Escalation (Costs are in 2016$ calculated to the end of the year).
12h.2 Decorative Metal Fencing & Gates 430 lf $ 252.00 $ 108,000
12h.3 Rolling Decorative Metal Gate 1 ea $ 27,000.00 $ 27,000
12i Fire safety equipment, fire alarms and emergency lighting
12i.1 Fire Alarm System 19,815 sf $ 5.40 $ 107,000
12i.2 Emergency Lighting 19,815 sf $ 1.40 $ 28,000
12j New public address/emergency communication
systems 19,815 sf $ 7.60 $ 151,000
12k Intrusion alarms 19,815 sf $ 1.80 $ 36,000
13 District Support Facilities $ - $ -
Not included in this Facilities Needs Assessment
14 Outdoor Learning Environments & Quads $ - $ -
14a Main Student Quad
14a.2 New Main Student Quad 10,725 sf $ 20.70
14b Learning Courts
14b.2 New Learning Court 12,500 sf $ 21.85
15 Exterior Play Spaces, Playfields & Hardcourts $ - $ -
15a Kindergarten Play Yard
15a.1 New Rubberized Surface Play Area 1,750 sf $ 20.00
15a.3 Shade Structure 1,200 sf $ 90.00
15b PE Play Yard & Hardcourts
15a.1 New Rubberized Surface Play Area 6,450 sf $ 20.00
15b.2 Elementary Play Apparatus 1 ea $ 63,000.00
15b.5 Resurface & Repair Hardcourts 21,000 sf $ 5.00
15b.6 New Hardcourts 34,750 sf $ 11.00
15b.8 Basketball Court/Sports Equipment 1 ls $ 25,333.33
Prepared by: LPA, Inc. / Cumming Prepared by: LPA, Inc. / Cumming
6.3 APPENDIX Facilities Master Plan 583
DETAILED PRIORITIZED COST ESTIMATE Lodi Unified School District