Page 611 - Facilities Master Plan 2016
P. 611

Lodi Unified School District                                            Lodi Unified School District
          Davis Elementary School                                                 Davis Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                   19-Apr-16
                           Project Cost Summary (2016$) - Davis Elementary School                 Project Cost Summary (2016$) - Davis Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
                                                                                   4b New Construction - Classrooms
          01 Modernize & Reconfigure Aging Classrooms      $           2,878,000 $                 3,828,000  4b.1 Remove Portable Classrooms                        5 ea  $       11,000.00
            1a Structural Strengthening                                             4b.3 Demolish Existing Buildings                5,820 sf  $               22.00
            1a.2 Wall strengthening             16,320 sf  $               13.50 $            220,000
            1b Replacement or repair of walls                                       4b.4 New Elementary Classroom Building (1-story)                4,224 sf  $             404.00
            1b.1 Replace walls                 16,320 sf  $               39.50 $            645,000  4b.10 Sitework & Site Improvements                4,224 sf  $               38.00
            1c Replacement or repair of windows                                    4d Student Collaboration Lab
            1c.1 Replace windows               16,320 sf  $               18.00 $            294,000  4d.1 New Student Collaboration Lab, 1- Story                1,056 sf  $             395.00
            1d Replacement or repair of doors (other than safety locks              4d.2 Sitework & Site Improvements                1,056 sf  $               38.00
            @ classroom doors)
            1d.1 Replace doors & hardware             16,320 sf  $               13.50 $            220,000
            1e Replacement or repair of floors                                    05 Maker Spaces & Science Labs                  $                       -  $                             -
            1e.1 Replace floors                16,320 sf  $               14.40 $            235,000  5a ES Science / Creativity Labs
            1f Replacement or repair of ceilings                                    5a.6 New ES Science / Creativity Labs Building                 3,080 sf  $             440.00
            1f.1 Replace ceilings              16,320 sf  $               27.00 $            441,000  5a.7 Sitework & Site Improvements                3,080 sf  $               38.00
            1g Patch & Paint Interior/Exterior
            1g.1 Patch & paint interior             16,320 sf  $                 3.10 $              51,000
            1g.2 Patch & paint exterior             16,320 sf  $                 4.50 $              73,000  06 Electives         $                       -  $                             -
            1o Replace Existing Roofing             28,195 sf  $               20.93 $            590,000  Not included in this Facilities Needs Assessment
            1p Repair Existing Covered Walkways / Hallways                8,380 sf  $               13.00 $            109,000
                                                                                  07 Performing Arts Improvements                 $                       -  $                             -
          02 Existing Building Systems & Toilets           $           1,513,000 $                 2,012,000  7a Music Lab
            2a HVAC system upgrades             16,320 sf  $               29.00 $            473,000  7a.4 New Music Lab                1,540 sf  $             449.00
                                                                                    7a.5 Sitework & Site Improvements                1,540 sf  $               38.00
            2b Lighting upgrades - new interior lighting & controls             16,320 sf  $               15.00 $            245,000
            2c Electrical upgrades
            2c.1 Upgrade electrical wiring & increase electrical                  08 Multi-Purpose Room / Food Service Improvements & Student Dining  $              589,000 $                    783,000
            outlets                            16,320 sf  $                 9.00 $            147,000  8a Elementary/Middle School multipurpose rooms  P3
            2d Plumbing system upgrades             16,320 sf  $               11.00 $            180,000  8a.2 Modernize Multipurpose Room                3,750 sf  $               99.00 $            371,000
            2e Replace aging plumbing, upgrade and/or expand                       8c Food service areas
            restroom facilities                                                     8c.6 New Trash Enclosure                        1 ea  $       45,000.00 $              45,000
            2e.2 Reconfigure Existing Restroom                1,575 sf  $             222.00 $            350,000  8d New Lunch Shelters                2,400 sf  $               72.00 $            173,000
            2f Energy-efficient building systems and controls (EMS
            system, per sf of Bldg)             16,320 sf  $                 7.20 $            118,000
                                                                                  09 Physical Education Improvements              $                       -  $                             -
                                                                                   9c PE/Fitness Labs
          03 Site Utilities                                $              698,000 $                    928,000  9c.4 New PE/Fitness Labs                2,112 sf  $             404.00
            (For entire campus and site)                                            9c.5 Sitework & Site Improvements                2,112 sf  $               38.00
            3a Updated gas service lines           583,704 sf  $                 0.28
            3b Updated sewer service lines           583,704 sf  $                 0.49
            3c Updated water service lines           583,704 sf  $                 0.63  10 Administration & Staff Support        $                       -  $                             -
            3d Updated electrical mains and distribution           583,704 sf  $                 0.90 $            525,000  10a Expanded, reorganized or relocated administration
            3e Updated storm drainage system           583,704 sf  $                 0.54  spaces
            3f Electrical Capacity Upgrades                        1 ls  $     172,500.00 $            173,000  10a.4 New Administration                2,046 sf  $             392.00
                                                                                    10a.5 Sitework & Site Improvements                2,046 sf  $               38.00
                                                                                   10b Staff Collaboration/Work Rooms
          04 Classrooms New Construction                   $                       -  $                             -
                                                                                    10b.4 New Staff Collaboration/Work Rooms                2,002 sf  $             392.00
                                                                                    10b.5 Sitework & Site Improvements                2,002 sf  $               38.00
            4a New Construction - Pre-School, DK & Kindergarten
            4a.2 New Pre-School, DK & Kindergarten Building                4,455 sf  $             395.00
            4a.4 Sitework & Site Improvements                4,455 sf  $               38.00
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.3       APPENDIX                                                                                                    Facilities Master Plan  582
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District