Page 616 - Facilities Master Plan 2016
P. 616
Lodi Unified School District Lodi Unified School District
Heritage Primary Elementary School Heritage Primary Elementary School
Facilities Master Plan - Total Program Cost Facilities Master Plan - Total Program Cost
Opinion of Probable Cost 19-Apr-16 Opinion of Probable Cost 19-Apr-16
Project Cost Summary (2016$) - Heritage Primary Elementary School Project Cost Summary (2016$) - Heritage Primary Elementary School
Construction Costs Total Project Construction Costs Total Project
Item Quantity Unit Unit Cost Subtotal Total Cost 25% (x 1.33) Item Quantity Unit Unit Cost Subtotal Total Cost 25% (x 1.33)
12 Safety, Security & Campus Control $ 1,267,000 $ 1,685,000 17 Technology Infrastructure $ 32,000 $ 32,000
12b Safety improvements to and/or new parent/bus drop-off areas and parking 17c MDF and IDF data rooms with environmental control
12b.1 New Parking Lot 17,000 sf $ 16.00 $ 272,000 (direct cost only) 1 ea $ 32,000.00 $ 32,000
12b.3 Entry Plaza 1,000 sf $ 26.00
12b.5 New Drop-off Area 3,200 sf $ 18.00 $ 58,000
12b.9 Repair existing Parking Lot 6,400 sf $ 6.30 $ 40,000 Total Construction/Project Cost (2016$) $ 7,791,000 $10,351,000
12b.11 New concrete walkways 1,500 sf $ 15.00 $ 23,000
12d Exterior lighting to ensure student safety 1 ls $ 40,000.00 $ 40,000
12e Safety locks at classroom doors 30 ea $ 449.00 $ 13,000 The following items are excluded from this budget:
12f Signage for emergency response and wayfinding 1 ls $ 32,000.00 $ 32,000 Utility hook-up fees & City connection fees.
12g Marquee Sign 1 ea $ 10,000.00 $ 10,000 Offsite work and traffic signals.
12h Fencing with controlled campus entrances Land acquisition costs.
12h.1 Chain Link Perimeter Fencing 350 lf $ 99.00 $ 35,000 Hazardous material surveys, abatement, and disposal.
12h.2 Decorative Metal Fencing & Gates 900 lf $ 252.00 $ 227,000 Escalation (Costs are in 2016$ calculated to the end of the year).
12h.3 Rolling Decorative Metal Gate 2 ea $ 27,000.00 $ 54,000
12h.4 Rolling Chain Link Gate 1 ea $ 25,200.00 $ 25,000
12i Fire safety equipment, fire alarms and emergency lighting
12i.1 Fire Alarm System 26,966 sf $ 5.40 $ 146,000
12i.2 Emergency Lighting 26,966 sf $ 1.40 $ 38,000
12j New public address/emergency communication
systems 26,966 sf $ 7.60 $ 205,000
12k Intrusion alarms 26,966 sf $ 1.80 $ 49,000
13 District Support Facilities $ - $ -
Not included in this Facilities Needs Assessment
14 Outdoor Learning Environments & Quads $ - $ -
14a Main Student Quad
14a.2 New Main Student Quad 7,200 sf $ 23.00
14b Learning Courts
14b.2 New Learning Court 1,600 sf $ 23.00
15 Exterior Play Spaces, Playfields & Hardcourts $ - $ -
15a Kindergarten Play Yard
15a.1 New Rubberized Surface Play Area 900 sf $ 20.00
15a.3 Shade Structure 1,200 sf $ 90.00
15b PE Play Yard & Hardcourts
15a.1 New Rubberized Surface Play Area 2,400 sf $ 20.00
15b.3 Relocate Elementary Play Apparatus 1 ea $ 18,000.00
15b.7 Slurry Coat & Stripe Existing Hardcourts 38,400 sf $ 3.00
15c Playfields
15c.1 Repair Playfields 40,800 sf $ 3.00
16 Next Generation Classroom Flexibility (Furniture) $ - $ -
16a Flexible furniture (Per Classroom, Direct Cost) 17 ea $ 15,000.00
Prepared by: LPA, Inc. / Cumming Prepared by: LPA, Inc. / Cumming
6.3 APPENDIX Facilities Master Plan 587
DETAILED PRIORITIZED COST ESTIMATE Lodi Unified School District