Page 616 - Facilities Master Plan 2016
P. 616

Lodi Unified School District                                            Lodi Unified School District
          Heritage Primary Elementary School                                      Heritage Primary Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                       Project Cost Summary (2016$) - Heritage Primary Elementary School       Project Cost Summary (2016$) - Heritage Primary Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          12 Safety, Security & Campus Control             $           1,267,000 $                 1,685,000  17 Technology Infrastructure  $                 32,000 $                      32,000
            12b Safety improvements to and/or new parent/bus drop-off areas and parking   17c MDF and IDF data rooms with environmental control
            12b.1 New Parking Lot              17,000 sf  $               16.00 $            272,000  (direct cost only)                         1 ea  $       32,000.00 $              32,000
            12b.3 Entry Plaza                     1,000 sf  $               26.00
            12b.5 New Drop-off Area                3,200 sf  $               18.00 $              58,000
            12b.9 Repair existing Parking Lot                6,400 sf  $                 6.30 $              40,000  Total Construction/Project Cost (2016$)  $           7,791,000  $10,351,000
            12b.11 New concrete walkways                1,500 sf  $               15.00 $              23,000
            12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000
            12e Safety locks at classroom doors                     30 ea  $             449.00 $              13,000  The following items are excluded from this budget:
            12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000  Utility hook-up fees & City connection fees.
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000  Offsite work and traffic signals.
            12h Fencing with controlled campus entrances                          Land acquisition costs.
            12h.1 Chain Link Perimeter Fencing                   350 lf  $               99.00 $              35,000  Hazardous material surveys, abatement, and disposal.
            12h.2 Decorative Metal Fencing & Gates                   900 lf  $             252.00 $            227,000  Escalation (Costs are in 2016$ calculated to the end of the year).
            12h.3 Rolling Decorative Metal Gate                        2 ea  $       27,000.00 $              54,000
            12h.4 Rolling Chain Link Gate                        1 ea  $       25,200.00 $              25,000
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System             26,966 sf  $                 5.40 $            146,000
            12i.2 Emergency Lighting             26,966 sf  $                 1.40 $              38,000
            12j New public address/emergency communication
            systems                            26,966 sf  $                 7.60 $            205,000
            12k Intrusion alarms               26,966 sf  $                 1.80 $              49,000
          13 District Support Facilities                   $                       -  $                             -
            Not included in this Facilities Needs Assessment
          14 Outdoor Learning Environments & Quads         $                       -  $                             -
            14a Main Student Quad
            14a.2 New Main Student Quad                7,200 sf  $               23.00
            14b Learning Courts
            14b.2 New Learning Court                1,600 sf  $               23.00
           15 Exterior Play Spaces, Playfields & Hardcourts  $                       -  $                             -
            15a Kindergarten Play Yard
            15a.1 New Rubberized Surface Play Area                   900 sf  $               20.00
            15a.3 Shade Structure                 1,200 sf  $               90.00
            15b PE Play Yard & Hardcourts
            15a.1 New Rubberized Surface Play Area                2,400 sf  $               20.00
            15b.3 Relocate Elementary Play Apparatus                        1 ea  $       18,000.00
            15b.7 Slurry Coat & Stripe Existing Hardcourts             38,400 sf  $                 3.00
            15c Playfields
            15c.1 Repair Playfields             40,800 sf  $                 3.00
           16 Next Generation Classroom Flexibility (Furniture)  $                       -  $                             -
            16a Flexible furniture (Per Classroom, Direct Cost)                     17 ea  $       15,000.00





         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  587
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District
   611   612   613   614   615   616   617   618   619   620   621