Page 621 - Facilities Master Plan 2016
P. 621

Lodi Unified School District                                            Lodi Unified School District
          Ellerth E. Larson Elementary School                                     Ellerth E. Larson Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                        Project Cost Summary (2016$) - Ellerth E. Larson Elementary School     Project Cost Summary (2016$) - Ellerth E. Larson Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          01 Modernize & Reconfigure Aging Classrooms      $                       -  $                             -  08 Multi-Purpose Room / Food Service Improvements & Student Dining  $                       -  $                             -
            1b Replacement or repair of walls                                      8a Elementary/Middle School multipurpose rooms
            1b.1 Replace walls                    1,920 sf  $               39.50   8a.3 Reconfigure Multipurpose Room                   800 sf  $             296.00  stage
            1e Replacement or repair of floors                                     8d New Lunch Shelters                  2,400 sf  $               72.00
            1e.1 Replace floors                   1,920 sf  $               14.40
            1f Replacement or repair of ceilings
            1f.1 Replace ceilings                 1,920 sf  $               27.00  09 Physical Education Improvements             $                       -  $                             -
            1g Patch & Paint Interior/Exterior                                     9c PE/Fitness Labs
            1g.1 Patch & paint interior                1,920 sf  $                 3.10  9c.4 New PE/Fitness Labs                2,112 sf  $             404.00
            1m Patch Existing Roofing                4,620 sf  $                 6.00  9c.5 Sitework & Site Improvements                2,112 sf  $               38.00
          02 Existing Building Systems & Toilets           $                       -  $                             -  10 Administration & Staff Support  $                       -  $                             -
            2e Replace aging plumbing, upgrade and/or expand                       10a Expanded, reorganized or relocated administration
            restroom facilities                                                    spaces
            2e.3 New Restroom                        750 sf  $             556.00   10a.3 Reconfigure Administration                   750 sf  $             235.00
            2e.4 Sitework & Site Improvements                   750 sf  $               57.00
                                                                                  11 Library & Student Support Services           $                       -  $                             -
          03 Site Utilities                                $                       -  $                             -  11d Learning Center
            Not included in this Facilities Needs Assessment                        11d.4 Reconfigure Learning Center                1,950 sf  $             237.00
          04 Classrooms New Construction                   $           5,082,000 $                 6,759,000  12 Safety, Security & Campus Control  $              890,000 $                 1,184,000
                                                                                   12b Safety improvements to and/or new parent/bus drop-off areas and parking
            4a New Construction - Pre-School, DK & Kindergarten  (5) K + (2) CR  P2 Growth  12b.1 New Parking Lot             16,800 sf  $               16.00 $            269,000
                                                                                    12b.5 New Drop-off Area             10,800 sf  $               18.00 $            194,000
            4a.2 New Pre-School, DK & Kindergarten Building                7,425 sf  $             395.00 $         2,933,000  12b.11 New concrete walkways                2,400 sf  $               15.00 $              36,000
            4a.4 Sitework & Site Improvements                7,425 sf  $               38.00 $            282,000  12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000
            4b New Construction - Classrooms                                       12e Safety locks at classroom doors                     50 ea  $             449.00 $              22,000
                                                                                   12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
            4b.4 New Elementary Classroom Building (1-story)                4,224 sf  $             404.00 $         1,706,000  12g Marquee Sign                        1 ea  $       10,000.00 $              10,000
            4b.10 Sitework & Site Improvements                4,224 sf  $               38.00 $            161,000
                                                                                   12h Fencing with controlled campus entrances
                                                                                    12h.2 Decorative Metal Fencing & Gates                   785 lf  $             252.00 $            198,000
                                                                                    12h.3 Rolling Decorative Metal Gate                        3 ea  $       27,000.00 $              81,000
          05 Maker Spaces & Science Labs                   $                       -  $                             -  12i Fire safety equipment, fire alarms and emergency lighting
            5a ES Science / Creativity Labs                                         12i.1 Fire Alarm System                4,620 sf  $                 5.40
            5a.6 New ES Science / Creativity Labs Building                 1,540 sf  $             440.00  12i.2 Emergency Lighting                4,620 sf  $                 1.40
            5a.7 Sitework & Site Improvements                1,540 sf  $               38.00  12j New public address/emergency communication
                                                                                   systems                                4,620 sf  $                 7.60
                                                                                   12k Intrusion alarms                   4,620 sf  $                 1.80 $                 8,000
          06 Electives                                     $                       -  $                             -
            Not included in this Facilities Needs Assessment
                                                                                  13 District Support Facilities                  $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
          07 Performing Arts Improvements                  $                       -  $                             -
            7a Music Lab
            7a.4 New Music Lab                    1,540 sf  $             449.00  14 Outdoor Learning Environments & Quads        $                       -  $                             -
            7a.5 Sitework & Site Improvements                1,540 sf  $               38.00  14b Learning Courts
                                                                                    14b.2 New Learning Court                3,600 sf  $               23.00
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  592
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District