Page 624 - Facilities Master Plan 2016
P. 624

Lodi Unified School District                                            Lodi Unified School District
          Lawrence Elementary School                                              Live Oak Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                     19-Apr-16  Opinion of Probable Cost                                    19-Apr-16
                          Project Cost Summary (2016$) - Lawrence Elementary School              Project Cost Summary (2016$) - Live Oak Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                       Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          Total Construction/Project Cost (2016$)          $           2,077,000  $2,761,000  01 Modernize & Reconfigure Aging Classrooms  $                       -  $                             -
                                                                                   1b Replacement or repair of walls
                                                                                    1b.2 Repair walls                     7,680 sf  $               12.60
          The following items are excluded from this budget:                       1c Replacement or repair of windows
           Utility hook-up fees & City connection fees.                             1c.1 Replace windows                  7,680 sf  $               18.00
           Offsite work and traffic signals.                                       1d Replacement or repair of doors (other than safety locks
           Land acquisition costs.                                                 @ classroom doors)
           Hazardous material surveys, abatement, and disposal.                     1d.1 Replace doors & hardware                7,680 sf  $               13.50
           Escalation (Costs are in 2016$ calculated to the end of the year).      1e Replacement or repair of floors
                                                                                    1e.2 Repair floors                    7,680 sf  $               10.80
                                                                                   1f Replacement or repair of ceilings
                                                                                    1f.2 Repair ceilings                  7,680 sf  $                 8.10
                                                                                   1g Patch & Paint Interior/Exterior
                                                                                    1g.1 Patch & paint interior                7,680 sf  $                 3.10
                                                                                    1g.2 Patch & paint exterior                7,680 sf  $                 4.50
                                                                                  02 Existing Building Systems & Toilets          $                       -  $                             -
                                                                                   2a HVAC system upgrades                7,680 sf  $               36.25
                                                                                   2b Lighting upgrades - new interior lighting & controls                7,680 sf  $               15.00
                                                                                   2c Electrical upgrades
                                                                                    2c.1 Upgrade electrical wiring & increase electrical
                                                                                    outlets                               7,680 sf  $                 9.00
                                                                                   2d Plumbing system upgrades                7,680 sf  $               11.00
                                                                                   2e Replace aging plumbing, upgrade and/or expand
                                                                                   restroom facilities
                                                                                    2e.1 Modernize Existing Restroom                   576 sf  $               83.00
                                                                                   2f Energy-efficient building systems and controls (EMS
                                                                                   system, per sf of Bldg)                7,680 sf  $                 7.20
                                                                                  03 Site Utilities                               $              313,000 $                    416,000
                                                                                   (For entire campus and site)
                                                                                   3a Updated gas service lines           292,723 sf  $                 0.20
                                                                                                                                         septic system
                                                                                   3b Updated sewer service lines           292,723 sf  $                 0.53  currently
                                                                                   3c Updated water service lines           292,723 sf  $                 0.68 $            198,000  replace water main
                                                                                   3d Updated electrical mains and distribution           292,723 sf  $                 0.90
                                                                                   3e Updated storm drainage system           292,723 sf  $                 0.45
                                                                                   3f Electrical Capacity Upgrades                        1 ls  $     115,000.00 $            115,000
                                                                                  04 Classrooms New Construction                  $           2,766,000 $                 3,679,000
                                                                                   4a New Construction - Pre-School, DK & Kindergarten  (2) K + (3) CR  P2
                                                                                    4a.2 New Pre-School, DK & Kindergarten Building                2,970 sf  $             395.00 $         1,173,000
                                                                                    4a.4 Sitework & Site Improvements                2,970 sf  $               38.00 $            113,000





         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  595
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District