Page 628 - Facilities Master Plan 2016
P. 628

Lodi Unified School District                                            Lodi Unified School District
          Lockeford Elementary School                                             Julia Morgan Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                     19-Apr-16  Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - Lockeford Elementary School             Project Cost Summary (2016$) - Julia Morgan Elementary School
                                                       Construction Costs   Total Project                                      Construction Costs   Total Project
          Item                       Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          Total Construction/Project Cost (2016$)          $           2,932,000  $3,899,000  01 Modernize & Reconfigure Aging Classrooms  $                       -  $                             -
                                                                                   1b Replacement or repair of walls
                                                                                    1b.1 Replace walls                    2,700 sf  $               39.50
          The following items are excluded from this budget:                        1b.2 Repair walls                  22,140 sf  $               12.60
           Utility hook-up fees & City connection fees.                            1c Replacement or repair of windows
           Offsite work and traffic signals.                                        1c.2 Repair windows                24,840 sf  $                 3.60
           Land acquisition costs.                                                 1d Replacement or repair of doors (other than safety locks
           Hazardous material surveys, abatement, and disposal.                    @ classroom doors)
           Escalation (Costs are in 2016$ calculated to the end of the year).       1d.2 Repair doors & hardware             24,840 sf  $                 4.50
                                                                                   1e Replacement or repair of floors
                                                                                    1e.1 Replace floors                   2,700 sf  $               14.40
                                                                                    1e.2 Repair floors                 22,140 sf  $               10.80
                                                                                   1f Replacement or repair of ceilings
                                                                                    1f.1 Replace ceilings                 2,700 sf  $               27.00
                                                                                    1f.2 Repair ceilings               22,140 sf  $                 8.10
                                                                                   1g Patch & Paint Interior/Exterior
                                                                                    1g.1 Patch & paint interior             24,840 sf  $                 3.10
                                                                                    1g.2 Patch & paint exterior             24,840 sf  $                 4.50
                                                                                   1o Replace Existing Roofing             42,280 sf  $               20.93
                                                                                   1p Repair Existing Covered Walkways / Hallways                1,580 sf  $               13.00
                                                                                  02 Existing Building Systems & Toilets          $                       -  $                             -
                                                                                   2a HVAC system upgrades             24,840 sf  $               29.00
                                                                                   2b Lighting upgrades - new interior lighting & controls             24,840 sf  $               15.00
                                                                                   2c Electrical upgrades
                                                                                    2c.1 Upgrade electrical wiring & increase electrical
                                                                                    outlets                            24,840 sf  $                 9.00
                                                                                   2d Plumbing system upgrades             24,840 sf  $               11.00
                                                                                   2e Replace aging plumbing, upgrade and/or expand
                                                                                   restroom facilities
                                                                                    2e.1 Modernize Existing Restroom                1,590 sf  $               83.00
                                                                                   2f Energy-efficient building systems and controls (EMS
                                                                                   system, per sf of Bldg)             24,840 sf  $                 7.20
                                                                                  03 Site Utilities                               $                       -  $                             -
                                                                                   (For entire campus and site)
                                                                                   3a Updated gas service lines           435,600 sf  $                 0.28
                                                                                   3b Updated sewer service lines           435,600 sf  $                 0.49
                                                                                   3c Updated water service lines           435,600 sf  $                 0.63
                                                                                   3d Updated electrical mains and distribution           435,600 sf  $                 0.72
                                                                                   3e Updated storm drainage system           435,600 sf  $                 0.63
                                                                                  04 Classrooms New Construction                  $                       -  $                             -
                                                                                   4b New Construction - Classrooms
                                                                                    4b.1 Remove Portable Classrooms                        6 ea  $       11,000.00
                                                                                    4b.3 Demolish Existing Buildings                   360 sf  $               22.00
                                                                                    4b.4 New Elementary Classroom Building (1-story)                6,000 sf  $             404.00
                                                                                    4b.10 Sitework & Site Improvements                6,000 sf  $               38.00

         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  599