Page 632 - Facilities Master Plan 2016
P. 632

Lodi Unified School District                                            Lodi Unified School District
          John Muir Elementary School                                             John Muir Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                     19-Apr-16  Opinion of Probable Cost                                   19-Apr-16
                         Project Cost Summary (2016$) - John Muir Elementary School              Project Cost Summary (2016$) - John Muir Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                       Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
                                                                                   4d Student Collaboration Lab
          01 Modernize & Reconfigure Aging Classrooms      $                       -  $                             -  4d.1 New Student Collaboration Lab, 1- Story                1,915 sf  $             426.60
            1b Replacement or repair of walls                                       4d.2 Sitework & Site Improvements                   958 sf  $               38.00
            1b.1 Replace walls                        960 sf  $               39.50
            1b.2 Repair walls                   23,820 sf  $               12.60
            1c Replacement or repair of windows                                   05 Maker Spaces & Science Labs                  $                       -  $                             -
            1c.2 Repair windows                 24,780 sf  $                 3.60  5a ES Science / Creativity Labs
            1d Replacement or repair of doors (other than safety locks              5a.6 New ES Science / Creativity Labs Building                 3,080 sf  $             440.00
            @ classroom doors)                                                      5a.7 Sitework & Site Improvements                3,080 sf  $               38.00
            1d.2 Repair doors & hardware             24,780 sf  $                 4.50
            1e Replacement or repair of floors
            1e.1 Replace floors                 24,780 sf  $               14.40  06 Electives                                    $                       -  $                             -
            1f Replacement or repair of ceilings                                   Not included in this Facilities Needs Assessment
            1f.1 Replace ceilings               24,780 sf  $               27.00
            1g Patch & Paint Interior/Exterior
            1g.1 Patch & paint interior             24,780 sf  $                 3.10  07 Performing Arts Improvements            $                       -  $                             -
            1g.2 Patch & paint exterior             24,780 sf  $                 4.50  7a Music Lab
            1m Patch Existing Roofing             35,330 sf  $                 6.00  7a.4 New Music Lab                   1,540 sf  $             449.00
                                                                                    7a.5 Sitework & Site Improvements                1,540 sf  $               38.00
          02 Existing Building Systems & Toilets           $                       -  $                             -
            2a HVAC system upgrades             24,780 sf  $               29.00  08 Multi-Purpose Room / Food Service Improvements & Student Dining  $           1,465,000 $                 1,948,000
                                                                                   8a Elementary/Middle School multipurpose rooms                P3
            2b Lighting upgrades - new interior lighting & controls             24,780 sf  $               15.00  8a.2 Modernize Multipurpose Room                2,700 sf  $               99.00 $            267,000
            2c Electrical upgrades                                                  8a.4 New Multipurpose Room                2,250 sf  $             494.00 $         1,112,000
            2c.1 Upgrade electrical wiring & increase electrical                    8a.5 Sitework & Site Improvements                2,250 sf  $               38.00 $              86,000
            outlets                             24,780 sf  $                 9.00  8c Food service areas
            2d Plumbing system upgrades             24,780 sf  $               11.00  8c.2 Modernize Food Service                1,200 sf  $             175.00
            2e Replace aging plumbing, upgrade and/or expand                        8c.6 New Trash Enclosure                        1 ea  $       45,000.00
            restroom facilities
            2e.1 Modernize Existing Restroom                2,400 sf  $               83.00
            2e.3 New Restroom                         200 sf  $             556.00  09 Physical Education Improvements            $                       -  $                             -
            2e.4 Sitework & Site Improvements                   200 sf  $               57.00
            2f Energy-efficient building systems and controls (EMS                 9c PE/Fitness Labs
            system, per sf of Bldg)             24,780 sf  $                 7.20   9c.4 New PE/Fitness Labs                2,112 sf  $             404.00
                                                                                    9c.5 Sitework & Site Improvements                2,112 sf  $               38.00
          03 Site Utilities                                $                       -  $                             -
            (For entire campus and site)                                          10 Administration & Staff Support               $                       -  $                             -
                                                                                   10a Expanded, reorganized or relocated administration
            3a Updated gas service lines           435,600 sf  $                 0.10
            3b Updated sewer service lines           435,600 sf  $                 0.18  spaces                           2,000 sf  $             118.00
                                                                                    10a.2 Modernize Administration
            3c Updated water service lines           435,600 sf  $                 0.23  10b Staff Collaboration/Work Rooms
            3d Updated electrical mains and distribution           435,600 sf  $                 0.63  10b.2 Modernize Staff Collaboration/Work Rooms                   500 sf  $             118.00
            3f Electrical Capacity Upgrades                        1 ls  $     115,000.00
                                                                                    10b.3 Reconfigure Staff Collaboration/Work Rooms                   500 sf  $             235.00
          04 Classrooms New Construction                   $                       -  $                             -  11 Library & Student Support Services  $                       -  $                             -
            4b New Construction - Classrooms                                       11a Elementary School Library/Innovation Lab
            4b.1 Remove Portable Classrooms                     11 ea  $       11,000.00
                                                                                    11a.2 New Library/Innovation Lab Building                4,290 sf  $             406.00
                                                                                    11a.5 Sitework & Site Improvements                4,290 sf  $               38.00
            4b.5 New Elementary Classroom Building (2-story)             11,491 sf  $             449.00
            4b.10 Sitework & Site Improvements                5,746 sf  $               38.00  11d Learning Center
                                                                                    11d.4 Reconfigure Learning Center                1,250 sf  $             237.00
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.3       APPENDIX                                                                                                    Facilities Master Plan  603
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District
   627   628   629   630   631   632   633   634   635   636   637