Page 634 - Facilities Master Plan 2016
P. 634

Lodi Unified School District                                            Lodi Unified School District
          Clyde W. Needham Elementary School                                      Clyde W. Needham Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                   19-Apr-16
                       Project Cost Summary (2016$) - Clyde W. Needham Elementary School      Project Cost Summary (2016$) - Clyde W. Needham Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          01 Modernize & Reconfigure Aging Classrooms      $           2,301,000 $                 3,060,000  04 Classrooms New Construction  $           3,053,000 $                 4,060,000
            1a Structural Strengthening
            1a.1 Roof/Wall connections                6,984 sf  $               19.30 $            135,000  4a New Construction - Pre-School, DK & Kindergarten  (2) K + (3) CR  P1
            1a.2 Wall strengthening                6,984 sf  $               13.50 $              94,000
            1b Replacement or repair of walls                                       4a.2 New Pre-School, DK & Kindergarten Building                2,970 sf  $             395.00 $         1,173,000
            1b.1 Replace walls                    6,984 sf  $               39.50 $            276,000  4a.4 Sitework & Site Improvements                2,970 sf  $               38.00 $            113,000
            1b.2 Repair walls                     7,680 sf  $               12.60 $              97,000  4b New Construction - Classrooms
            1c Replacement or repair of windows                                     4b.1 Remove Portable Classrooms                        8 ea  $       11,000.00 $              88,000
            1c.1 Replace windows               14,664 sf  $               18.00 $            264,000  4b.3 Demolish Existing Buildings             12,685 sf  $               22.00 $            279,000
            1d Replacement or repair of doors (other than safety locks
            @ classroom doors)                                                      4b.4 New Elementary Classroom Building (1-story)                3,168 sf  $             404.00 $         1,280,000
            1d.1 Replace doors & hardware             14,664 sf  $               13.50 $            198,000  4b.10 Sitework & Site Improvements                3,168 sf  $               38.00 $            120,000
            1e Replacement or repair of floors
            1e.1 Replace floors                   6,984 sf  $               14.40 $            101,000
            1e.2 Repair floors                    7,680 sf  $               10.80 $              83,000  05 Maker Spaces & Science Labs  $           1,234,000 $                 1,641,000
            1f Replacement or repair of ceilings                                   5a ES Science / Creativity Labs                            P1 Mod.
            1f.1 Replace ceilings                 6,984 sf  $               27.00 $            189,000  5a.4 Structural Upgrade to Existing Building                 1,575 sf  $               72.30 $            114,000
            1f.2 Repair ceilings                  7,680 sf  $                 8.10 $              62,000
            1g Patch & Paint Interior/Exterior                                      5a.5 Reconfigure ES Science / Creativity Labs Building                 1,575 sf  $             243.00 $            383,000
            1g.1 Patch & paint interior             14,664 sf  $                 3.10 $              45,000  5a.6 New ES Science / Creativity Labs Building                 1,540 sf  $             440.00 $            678,000
            1o Replace Existing Roofing             31,137 sf  $               20.93 $            652,000  5a.7 Sitework & Site Improvements                1,540 sf  $               38.00 $              59,000
            1p Repair Existing Covered Walkways / Hallways                8,090 sf  $               13.00 $            105,000
                                                                                  06 Electives                                    $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
          02 Existing Building Systems & Toilets           $           1,220,000 $                 1,623,000
            2a HVAC system upgrades             14,664 sf  $               29.00 $            425,000
            2b Lighting upgrades - new interior lighting & controls             14,664 sf  $               15.00 $            220,000  07 Performing Arts Improvements  $              467,000 $                    621,000
            2c Electrical upgrades                                                 7a Music Lab                                              P3 w/ MPR
            2c.1 Upgrade electrical wiring & increase electrical                    7a.3 Reconfigure Music Lab                1,728 sf  $             270.00 $            467,000
            outlets                            14,664 sf  $                 9.00 $            132,000
            2d Plumbing system upgrades             14,664 sf  $               11.00 $            161,000
            2e Replace aging plumbing, upgrade and/or expand                      08 Multi-Purpose Room / Food Service Improvements & Student Dining  $           1,800,000 $                 2,394,000
            restroom facilities                                                    8a Elementary/Middle School multipurpose rooms                P3
            2e.2 Reconfigure Existing Restroom                   600 sf  $             222.00 $            133,000  8a.4 New Multipurpose Room                3,300 sf  $             494.00 $         1,630,000
            2e.3 Structural Upgrade to Existing Building                   600 sf  $               72.30 $              43,000  8a.5 Sitework & Site Improvements                3,300 sf  $               38.00 $            125,000
            2f Energy-efficient building systems and controls (EMS                 8c Food service areas
            system, per sf of Bldg)             14,664 sf  $                 7.20 $            106,000  8c.6 New Trash Enclosure                        1 ea  $       45,000.00 $              45,000
          03 Site Utilities                                $              590,000 $                    785,000  09 Physical Education Improvements  $                       -  $                             -
            (For entire campus and site)                                           9c PE/Fitness Labs
            3a New gas service lines           307,305 sf  $                 0.32   9c.4 New PE/Fitness Labs                2,112 sf  $             404.00
            3b New sewer service lines           307,305 sf  $                 0.63  9c.5 Sitework & Site Improvements                2,112 sf  $               38.00
            3c New water service lines           307,305 sf  $                 0.68
            3d New electrical mains and distribution           307,305 sf  $                 1.17 $            360,000
            3e New storm drainage system           307,305 sf  $                 0.68  10 Administration & Staff Support          $                       -  $                             -
            3f Electrical Capacity Upgrades                        1 ls  $     230,000.00 $            230,000  10a Expanded, reorganized or relocated administration
                                                                                   spaces
                                                                                    10a.3 Reconfigure Administration                1,720 sf  $             235.00
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  605
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District
   629   630   631   632   633   634   635   636   637   638   639