Page 638 - Facilities Master Plan 2016
P. 638

Lodi Unified School District                                            Lodi Unified School District
          Oakwood Elementary School                                               Oakwood Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                     19-Apr-16  Opinion of Probable Cost                                    19-Apr-16
                          Project Cost Summary (2016$) - Oakwood Elementary School               Project Cost Summary (2016$) - Oakwood Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                       Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          01 Modernize & Reconfigure Aging Classrooms      $                       -  $                             -  04 Classrooms New Construction  $           3,192,000 $                 4,245,000
            1b Replacement or repair of walls                                      4b New Construction - Classrooms                              P2
            1b.1 Replace walls                     3,180 sf  $               39.50  4b.1 Remove Portable Classrooms                        5 ea  $       11,000.00 $              55,000
            1b.2 Repair walls                   10,380 sf  $               12.60    4b.2 Relocate Portable Classrooms                        3 ea  $       25,000.00 $              75,000
            1c Replacement or repair of windows
            1c.1 Replace windows                13,560 sf  $               18.00    4b.4 New Elementary Classroom Building (1-story)                1,056 sf  $             404.00
            1d Replacement or repair of doors (other than safety locks
            @ classroom doors)                                                      4b.5 New Elementary Classroom Building (2-story)                5,280 sf  $             449.00 $         2,371,000
            1d.1 Replace doors & hardware             13,560 sf  $               13.50  4b.10 Sitework & Site Improvements                5,280 sf  $               38.00 $            201,000
            1e Replacement or repair of floors                                     4d Student Collaboration Lab
            1e.1 Replace floors                 13,560 sf  $               14.40    4d.1 New Student Collaboration Lab, 1- Story                1,056 sf  $             426.60 $            450,000
            1f Replacement or repair of ceilings                                    4d.2 Sitework & Site Improvements                1,056 sf  $               38.00 $              40,000
            1f.1 Replace ceilings                  3,180 sf  $               27.00
            1f.2 Repair ceilings                10,380 sf  $                 8.10
            1g Patch & Paint Interior/Exterior                                    05 Maker Spaces & Science Labs                  $                       -  $                             -
            1g.1 Patch & paint interior             13,560 sf  $                 3.10  5a ES Science / Creativity Labs
            1g.2 Patch & paint exterior             13,560 sf  $                 4.50  5a.6 New ES Science / Creativity Labs Building                 3,724 sf  $             475.20
            1o Replace Existing Roofing             28,826 sf  $               20.93  5a.7 Sitework & Site Improvements                1,862 sf  $               38.00
            1p Repair Existing Covered Walkways / Hallways                   825 sf  $               13.00
                                                                                  06 Electives                                    $                       -  $                             -
          02 Existing Building Systems & Toilets           $                       -  $                             -  Not included in this Facilities Needs Assessment
            2a HVAC system upgrades             13,560 sf  $               29.00
            2b Lighting upgrades - new interior lighting & controls             13,560 sf  $               15.00  07 Performing Arts Improvements  $                       -  $                             -
            2c Electrical upgrades                                                 7a Music Lab
            2c.1 Upgrade electrical wiring & increase electrical                    7a.4 New Music Lab                    1,540 sf  $             449.00
            outlets                             13,560 sf  $                 9.00   7a.5 Sitework & Site Improvements                1,540 sf  $               38.00
            2d Plumbing system upgrades             13,560 sf  $               11.00
            2e Replace aging plumbing, upgrade and/or expand
            restroom facilities                                                   08 Multi-Purpose Room / Food Service Improvements & Student Dining  $                       -  $                             -
            2e.1 Modernize Existing Restroom                1,429 sf  $               83.00  8a Elementary/Middle School multipurpose rooms
            2f Energy-efficient building systems and controls (EMS                  8a.2 Modernize Multipurpose Room                3,912 sf  $               99.00
            system, per sf of Bldg)             13,560 sf  $                 7.20
                                                                                   8c Food service areas
                                                                                    8c.2 Modernize Food Service                1,260 sf  $             175.00
                                                                                    8c.6 New Trash Enclosure                        1 ea  $       45,000.00
          03 Site Utilities                                $                       -  $                             -
            (For entire campus and site)
            3a Updated gas service lines           348,480 sf  $                 0.30  09 Physical Education Improvements         $                       -  $                             -
            3b Updated sewer service lines           348,480 sf  $                 0.53  9c PE/Fitness Labs
            3c Updated water service lines           348,480 sf  $                 0.68  9c.4 New PE/Fitness Labs                2,112 sf  $             404.00
            3d Updated electrical mains and distribution           348,480 sf  $                 0.90  9c.5 Sitework & Site Improvements                2,112 sf  $               38.00
            3e Updated storm drainage system           348,480 sf  $                 0.68
            3f Electrical Capacity Upgrades                        1 ls  $     172,500.00
                                                                                  10 Administration & Staff Support               $                       -  $                             -
                                                                                   10a Expanded, reorganized or relocated administration
                                                                                   spaces
                                                                                    10a.3 Reconfigure Administration                1,500 sf  $             235.00
                                                                                    10a.4 New Administration                1,200 sf  $             392.00
                                                                                    10a.5 Sitework & Site Improvements                1,200 sf  $               38.00
                                                                                   10b Staff Collaboration/Work Rooms
                                                                                    10b.2 Modernize Staff Collaboration/Work Rooms                   520 sf  $             118.00
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.3       APPENDIX                                                                                                    Facilities Master Plan  609