Lodi Unified School District                                           Lodi Unified School District
          Podesta Ranch Elementary School                                        Erma B. Reese Elementary School
          Facilities Master Plan - Total Program Cost                            Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                     19-Apr-16  Opinion of Probable Cost                                   19-Apr-16
                        Project Cost Summary (2016$) - Podesta Ranch Elementary School         Project Cost Summary (2016$) - Erma B. Reese Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                       Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item   Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
           17 Technology Infrastructure                    $                       -  $                             -  01 Modernize & Reconfigure Aging Classrooms  $                648,000 $                    862,000
            Not included in this Facilities Needs Assessment                       1b Replacement or repair of walls                      P2 K CR's Reconfig.
                                                                                   1b.1 Replace walls                    5,400 sf  $               39.50 $             213,000
                                                                                   1b.2 Repair walls                     9,600 sf  $               12.60
          Total Construction/Project Cost (2016$)          $                 27,000  $36,000  1c Replacement or repair of windows
                                                                                   1c.1 Replace windows                  5,400 sf  $               18.00 $               97,000
                                                                                   1d Replacement or repair of doors (other than safety locks
          The following items are excluded from this budget:                       @ classroom doors)
           Utility hook-up fees & City connection fees.                            1d.1 Replace doors & hardware                5,400 sf  $               13.50 $               73,000
           Offsite work and traffic signals.                                       1e Replacement or repair of floors
           Land acquisition costs.                                                 1e.1 Replace floors                   5,400 sf  $               14.40 $               78,000
           Hazardous material surveys, abatement, and disposal.                    1e.2 Repair floors                    9,600 sf  $               10.80
           Escalation (Costs are in 2016$ calculated to the end of the year).      1f Replacement or repair of ceilings
                                                                                   1f.1 Replace ceilings                 5,400 sf  $               27.00 $             146,000
                                                                                   1f.2 Repair ceilings                  9,600 sf  $                 8.10
                                                                                   1g Patch & Paint Interior/Exterior
                                                                                   1g.1 Patch & paint interior                5,400 sf  $                 3.10 $               17,000
                                                                                   1g.2 Patch & paint exterior                5,400 sf  $                 4.50 $               24,000
                                                                                   1o Replace Existing Roofing             24,460 sf  $               20.93
                                                                                   1p Repair Existing Covered Walkways / Hallways             11,900 sf  $               13.00
                                                                                 02 Existing Building Systems & Toilets          $                711,000 $                    946,000
                                                                                   2a HVAC system upgrades                5,400 sf  $               29.00 $             157,000  P2 K CR's Reconfig.
                                                                                   2b Lighting upgrades - new interior lighting & controls                5,400 sf  $               15.00 $               81,000
                                                                                   2c Electrical upgrades
                                                                                   2c.1 Upgrade electrical wiring & increase electrical
                                                                                   outlets                               5,400 sf  $                 9.00 $               49,000
                                                                                   2d Plumbing system upgrades                5,400 sf  $               11.00 $               59,000
                                                                                   2e Replace aging plumbing, upgrade and/or expand
                                                                                   restroom facilities
                                                                                   2e.1 Modernize Existing Restroom                1,200 sf  $               83.00 $             100,000
                                                                                   2e.3 New Restroom                        432 sf  $             556.00 $             240,000
                                                                                   2e.4 Sitework & Site Improvements                   432 sf  $               57.00 $               25,000
                                                                                   2f Energy-efficient building systems and controls (EMS
                                                                                   system, per sf of Bldg)                5,400 sf  $                 7.20
                                                                                 03 Site Utilities                               $                475,000 $                    632,000
                                                                                   (For entire campus and site)                                 P2
                                                                                   3a Updated gas service lines           399,881 sf  $                 0.20
                                                                                   3b Updated sewer service lines           399,881 sf  $                 0.35
                                                                                   3c Updated water service lines           399,881 sf  $                 0.45
                                                                                   3d Updated electrical mains and distribution           399,881 sf  $                 0.90 $             360,000
                                                                                   3e Updated storm drainage system           399,881 sf  $                 0.45
                                                                                   3f Electrical Capacity Upgrades                        1 ls  $     115,000.00 $             115,000




         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  614
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District
   638   639   640   641   642   643   644   645   646   647   648