Lodi Unified School District                                           Lodi Unified School District
          Erma B. Reese Elementary School                                        Erma B. Reese Elementary School
          Facilities Master Plan - Total Program Cost                            Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16  Opinion of Probable Cost                                    19-Apr-16
                        Project Cost Summary (2016$) - Erma B. Reese Elementary School         Project Cost Summary (2016$) - Erma B. Reese Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          04 Classrooms New Construction                  $             6,954,000 $                 9,249,000  11 Library & Student Support Services  $                         -  $                             -
           4b New Construction - Classrooms                              P2        11a Elementary School Library/Innovation Lab
            4b.1 Remove Portable Classrooms                     15 ea  $       11,000.00 $             165,000  11a.2 New Library/Innovation Lab Building                4,290 sf  $             406.00
                                                                                   11a.5 Sitework & Site Improvements                4,290 sf  $               38.00
            4b.4 New Elementary Classroom Building (1-story)             16,896 sf  $             323.20 $          5,461,000  11d Learning Center
            4b.10 Sitework & Site Improvements             16,896 sf  $               38.00 $             642,000  11d.4 Reconfigure Learning Center                1,710 sf  $             237.00
           4d Student Collaboration Lab
            4d.1 New Student Collaboration Lab, 1- Story                1,584 sf  $             395.00 $             626,000
            4d.2 Sitework & Site Improvements                1,584 sf  $               38.00 $               60,000  12 Safety, Security & Campus Control  $             1,400,000 $                 1,862,000
                                                                                   12a  Remaining asbestos removal             12,560 sf  $                 4.00 $               50,000
                                                                                   12b Safety improvements to and/or new parent/bus drop-off areas and parking
          05 Maker Spaces & Science Labs                  $                         -  $                             -  12b.1 New Parking Lot             30,625 sf  $               16.00 $             490,000
           5a ES Science / Creativity Labs                                         12b.3 Entry Plaza                     1,500 sf  $               26.00
            5a.6 New ES Science / Creativity Labs Building                 3,080 sf  $             440.00  12b.5 New Drop-off Area             15,275 sf  $               18.00 $             275,000
            5a.7 Sitework & Site Improvements                3,080 sf  $               38.00  12b.11 New concrete walkways                6,800 sf  $               15.00 $             102,000
                                                                                   12c Covered Walkway                      640 sf  $               90.00 $               58,000
                                                                                   12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $               40,000
          06 Electives                                    $                         -  $                             -  12e Safety locks at classroom doors                     25 ea  $             449.00 $               11,000
           Not included in this Facilities Needs Assessment                        12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $               32,000
                                                                                   12g Marquee Sign                              1 ea  $       10,000.00 $               10,000
                                                                                   12h Fencing with controlled campus entrances
          07 Performing Arts Improvements                 $                         -  $                             -  12h.2 Decorative Metal Fencing & Gates                   400 lf  $             252.00 $             101,000
           7a Music Lab                                                            12h.3 Rolling Decorative Metal Gate                        1 ea  $       27,000.00 $               27,000
            7a.4 New Music Lab                    1,540 sf  $             449.00   12i Fire safety equipment, fire alarms and emergency lighting
            7a.5 Sitework & Site Improvements                1,540 sf  $               38.00  12i.1 Fire Alarm System             12,560 sf  $                 5.40 $               68,000
                                                                                   12i.2 Emergency Lighting             12,560 sf  $                 1.40 $               18,000
                                                                                   12j New public address/emergency communication
          08 Multi-Purpose Room / Food Service Improvements & Student Dining  $                946,000 $                 1,258,000  systems              12,560 sf  $                 7.60 $               95,000
           8a Elementary/Middle School multipurpose rooms                          12k Intrusion alarms               12,560 sf  $                 1.80 $               23,000
            8a.2 Modernize Multipurpose Room                3,500 sf  $               99.00 $             347,000
            8a.4 New Multipurpose Room                1,125 sf  $             494.00 $             556,000
            8a.5 Sitework & Site Improvements                1,125 sf  $               38.00 $               43,000  13 District Support Facilities  $                         -  $                             -
           8c Food service areas                                                   Not included in this Facilities Needs Assessment
            8c.2 Modernize Food Service                   750 sf  $             175.00
            8c.6 New Trash Enclosure                        1 ea  $       45,000.00
           8d New Lunch Shelters                  2,400 sf  $               72.00  14 Outdoor Learning Environments & Quads      $                         -  $                             -
                                                                                   14b Learning Courts
                                                                                   14b.2 New Learning Court                9,750 sf  $               20.70
          09 Physical Education Improvements              $                         -  $                             -
           9c PE/Fitness Labs
            9c.4 New PE/Fitness Labs                2,112 sf  $             404.00  15 Exterior Play Spaces, Playfields & Hardcourts  $                281,000 $                    374,000
            9c.5 Sitework & Site Improvements                2,112 sf  $               38.00  15a Kindergarten Play Yard                      P2 w/ K
                                                                                   15a.1 New Rubberized Surface Play Area                1,400 sf  $               20.00 $               28,000
                                                                                   15a.3 Shade Structure                 1,200 sf  $               90.00 $             108,000
          10 Administration & Staff Support               $                         -  $                             -  15a.5 Resurface & Repair Hardcourts                2,250 sf  $                 5.00 $               11,000
           10a Expanded, reorganized or relocated administration                   15a.6 New Hardcourts               12,200 sf  $               11.00 $             134,000
           spaces                                                                  15b PE Play Yard & Hardcourts
            10a.4 New Administration                1,980 sf  $             392.00  15a.1 New Rubberized Surface Play Area                4,000 sf  $               20.00
            10a.5 Sitework & Site Improvements                1,980 sf  $               38.00  15b.2 Elementary Play Apparatus                        1 ea  $       63,000.00
           10b Staff Collaboration/Work Rooms                                      15b.3 Relocate Elementary Play Apparatus                        1 ea  $       18,000.00
            10b.4 New Staff Collaboration/Work Rooms                1,980 sf  $             392.00  15b.5 Resurface & Repair Hardcourts             17,400 sf  $                 5.00
            10b.5 Sitework & Site Improvements                1,980 sf  $               38.00  15b.6 New Hardcourts             50,275 sf  $               11.00
                                                                                   15b.8 Basketball Court/Sports Equipment                        1 ls  $       38,000.00
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.3       APPENDIX                                                                                                    Facilities Master Plan  615
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District
   639   640   641   642   643   644   645   646   647   648   649