          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - Manlio Silva Elementary School          Project Cost Summary (2016$) - Manlio Silva Elementary School
                                                       Construction Costs   Total Project                                      Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
                                                                                   15c Playfields
          08 Multi-Purpose Room / Food Service Improvements & Student Dining  $                       -  $                             -  15c.1 Repair Playfields           128,800 sf  $                 3.00
            8a Elementary/Middle School multipurpose rooms                         15d Baseball/Softball Fields
            8a.3 Reconfigure Multipurpose Room                   800 sf  $             296.00  stage  15d.4 Backstops, per field                        1 ea  $       27,000.00
            8d New Lunch Shelters                 2,400 sf  $               72.00
                                                                                  16 Next Generation Classroom Flexibility (Furniture)  $                       -  $                             -
          09 Physical Education Improvements               $                       -  $                             -  16a Flexible furniture (Per Classroom, Direct Cost)                     31 ea  $         7,500.00
            9c PE/Fitness Labs
            9c.4 New PE/Fitness Labs                2,112 sf  $             404.00
            9c.5 Sitework & Site Improvements                2,112 sf  $               38.00  17 Technology Infrastructure        $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
          10 Administration & Staff Support                $                       -  $                             -
            10a Expanded, reorganized or relocated administration                 Total Construction/Project Cost (2016$)         $              122,000  $162,000
            spaces
            10a.3 Reconfigure Administration                   750 sf  $             235.00
                                                                                  The following items are excluded from this budget:
                                                                                   Utility hook-up fees & City connection fees.
          11 Library & Student Support Services            $                       -  $                             -  Offsite work and traffic signals.
            11d Learning Center                                                    Land acquisition costs.
            11d.4 Reconfigure Learning Center                1,920 sf  $             237.00  Hazardous material surveys, abatement, and disposal.
                                                                                   Escalation (Costs are in 2016$ calculated to the end of the year).
          12 Safety, Security & Campus Control             $              122,000 $                    162,000
            12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000
            12e Safety locks at classroom doors                     45 ea  $             449.00 $              20,000
            12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000
            12h Fencing with controlled campus entrances
            12h.2 Decorative Metal Fencing & Gates                     40 lf  $             252.00 $              10,000
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System                5,306 sf  $                 5.40
            12i.2 Emergency Lighting                5,306 sf  $                 1.40
            12j New public address/emergency communication
            systems                               5,306 sf  $                 7.60
            12k Intrusion alarms                  5,306 sf  $                 1.80 $              10,000
          13 District Support Facilities                   $                       -  $                             -
            Not included in this Facilities Needs Assessment
          14 Outdoor Learning Environments & Quads         $                       -  $                             -
            Not included in this Facilities Needs Assessment

           15 Exterior Play Spaces, Playfields & Hardcourts  $                       -  $                             -
            15a Kindergarten Play Yard
            15a.1 New Rubberized Surface Play Area                1,963 sf  $               18.75
            15a.3 Shade Structure                 1,200 sf  $               90.00
            15b PE Play Yard & Hardcourts
            15a.1 New Rubberized Surface Play Area                6,000 sf  $               20.00
            15b.2 Elementary Play Apparatus                        1 ea  $       63,000.00
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  617
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District
   641   642   643   644   645   646   647   648   649   650   651