Page 645 - Facilities Master Plan 2016
P. 645

Lodi Unified School District                                            Lodi Unified School District
          Erma B. Reese Elementary School                                         Manlio Silva Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                     19-Apr-16  Opinion of Probable Cost                                    19-Apr-16
                        Project Cost Summary (2016$) - Erma B. Reese Elementary School          Project Cost Summary (2016$) - Manlio Silva Elementary School
                                                       Construction Costs   Total Project                                      Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
           15c Playfields
            15c.1 Repair Playfields           104,600 sf  $                 3.00  01 Modernize & Reconfigure Aging Classrooms     $                       -  $                             -
                                                                                   1b Replacement or repair of walls
                                                                                    1b.1 Replace walls                       960 sf  $               39.50
          16 Next Generation Classroom Flexibility (Furniture)  $                         -  $                             -  1b.2 Repair walls                1,676 sf  $               12.60
           16a Flexible furniture (Per Classroom, Direct Cost)                     15 ea  $       15,000.00  1e Replacement or repair of floors
                                                                                    1e.1 Replace floors                      960 sf  $               14.40
                                                                                    1e.2 Repair floors                    1,676 sf  $               10.80
          17 Technology Infrastructure                     $                         -  $                             -  1f Replacement or repair of ceilings
           Not included in this Facilities Needs Assessment                         1f.1 Replace ceilings                    960 sf  $               27.00
                                                                                    1f.2 Repair ceilings                  1,676 sf  $                 8.10
                                                                                   1g Patch & Paint Interior/Exterior
          Total Construction/Project Cost (2016$)          $           11,415,000  $15,183,000  1g.1 Patch & paint interior                2,636 sf  $                 3.10
          The following items are excluded from this budget:                      02 Existing Building Systems & Toilets          $                       -  $                             -
           Utility hook-up fees & City connection fees.                            Not included in this Facilities Needs Assessment
           Offsite work and traffic signals.
           Land acquisition costs.
           Hazardous material surveys, abatement, and disposal.                   03 Site Utilities                               $                       -  $                             -
           Escalation (Costs are in 2016$ calculated to the end of the year).      Not included in this Facilities Needs Assessment
                                                                                  04 Classrooms New Construction                  $                       -  $                             -
                                                                                   4a New Construction - Pre-School, DK & Kindergarten
                                                                                    4a.2 New Pre-School, DK & Kindergarten Building                2,970 sf  $             395.00
                                                                                    4a.4 Sitework & Site Improvements                2,970 sf  $               38.00
                                                                                   4b New Construction - Classrooms
                                                                                    4b.1 Remove Portable Classrooms                        1 ea  $       11,000.00
                                                                                    4b.4 New Elementary Classroom Building (1-story)                4,224 sf  $             404.00
                                                                                    4b.10 Sitework & Site Improvements                4,224 sf  $               38.00
                                                                                   4d Student Collaboration Lab
                                                                                    4d.1 New Student Collaboration Lab, 1- Story                   528 sf  $             395.00
                                                                                    4d.2 Sitework & Site Improvements                   528 sf  $               38.00
                                                                                  05 Maker Spaces & Science Labs                  $                       -  $                             -
                                                                                   5a ES Science / Creativity Labs
                                                                                    5a.6 New ES Science / Creativity Labs Building                 3,080 sf  $             440.00
                                                                                    5a.7 Sitework & Site Improvements                3,080 sf  $               38.00
                                                                                  06 Electives                                    $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
                                                                                  07 Performing Arts Improvements                 $                       -  $                             -
                                                                                   7a Music Lab
                                                                                    7a.4 New Music Lab                    1,540 sf  $             449.00
                                                                                    7a.5 Sitework & Site Improvements                1,540 sf  $               38.00


         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  616
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District
   640   641   642   643   644   645   646   647   648   649   650