Page 648 - Facilities Master Plan 2016
P. 648

Lodi Unified School District                                            Lodi Unified School District
          Sutherland Elementary School                                            Sutherland Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - Sutherland Elementary School             Project Cost Summary (2016$) - Sutherland Elementary School
                                                       Construction Costs   Total Project                                      Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
            11d Learning Center
            11d.3 Modernize Learning Center                   600 sf  $             119.00  Total Construction/Project Cost (2016$)  $              823,000  $1,095,000
            11d.4 Reconfigure Learning Center                1,160 sf  $             237.00
                                                                                  The following items are excluded from this budget:
          12 Safety, Security & Campus Control             $              823,000 $                 1,095,000  Utility hook-up fees & City connection fees.
            12b Safety improvements to and/or new parent/bus drop-off areas and parking  Offsite work and traffic signals.
            12b.1 New Parking Lot              38,350 sf  $               16.00 $            307,000 Reconfig. Pkg. @ 50%  Land acquisition costs.
            12b.5 New Drop-off Area                9,800 sf  $               18.00 $            176,000  Hazardous material surveys, abatement, and disposal.
            12b.11 New concrete walkways                4,300 sf  $               15.00 $              65,000  Escalation (Costs are in 2016$ calculated to the end of the year).
            12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000
            12e Safety locks at classroom doors                     35 ea  $             449.00 $              16,000
            12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000
            12h Fencing with controlled campus entrances
            12h.2 Decorative Metal Fencing & Gates                   440 lf  $             252.00 $            111,000
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System             36,549 sf  $                 5.40
            12i.2 Emergency Lighting             36,549 sf  $                 1.40
            12j New public address/emergency communication
            systems                            36,549 sf  $                 7.60
            12k Intrusion alarms               36,549 sf  $                 1.80 $              66,000
          13 District Support Facilities                   $                       -  $                             -
            Not included in this Facilities Needs Assessment
          14 Outdoor Learning Environments & Quads         $                       -  $                             -
            14b Learning Courts
            14b.2 New Learning Court                6,600 sf  $               23.00
           15 Exterior Play Spaces, Playfields & Hardcourts  $                       -  $                             -
            15a Kindergarten Play Yard
            15a.1 New Rubberized Surface Play Area                1,750 sf  $               20.00
            15a.3 Shade Structure                 1,200 sf  $               90.00
            15b PE Play Yard & Hardcourts
            15a.1 New Rubberized Surface Play Area                4,700 sf  $               20.00
            15b.4 Shade Structure                 2,400 sf  $               90.00
            15b.5 Resurface & Repair Hardcourts             62,450 sf  $                 5.00
            15c Playfields
            15c.1 Repair Playfields           148,725 sf  $                 3.00
           16 Next Generation Classroom Flexibility (Furniture)  $                       -  $                             -
            16a Flexible furniture (Per Classroom, Direct Cost)                     21 ea  $       15,000.00
           17 Technology Infrastructure                    $                       -  $                             -
            Not included in this Facilities Needs Assessment




         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  619