Page 641 - Facilities Master Plan 2016
P. 641

Lodi Unified School District                                            Lodi Unified School District
          Parklane Elementary School                                              Parklane Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                          Project Cost Summary (2016$) - Parklane Elementary School              Project Cost Summary (2016$) - Parklane Elementary School
                                                       Construction Costs   Total Project                                      Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          12 Safety, Security & Campus Control            $              903,000 $                 1,201,000  Total Construction/Project Cost (2016$)  $           3,812,000  $5,070,000
            12b Safety improvements to and/or new parent/bus drop-off areas and parking
            12b.1 New Parking Lot              17,400 sf  $               16.00 $            278,000
            12b.9 Repair existing Parking Lot             12,500 sf  $                 6.30 $              79,000  The following items are excluded from this budget:
            12b.10 Slurry Coat & Stripe Existing Paving             21,600 sf  $                 2.00 $              43,000  Utility hook-up fees & City connection fees.
            12b.11 New concrete walkways                1,250 sf  $               15.00 $              19,000  Offsite work and traffic signals.
            12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000  Land acquisition costs.
            12e Safety locks at classroom doors                     45 ea  $             449.00 $              20,000  Hazardous material surveys, abatement, and disposal.
            12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000  Escalation (Costs are in 2016$ calculated to the end of the year).
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000
            12h Fencing with controlled campus entrances
            12h.2 Decorative Metal Fencing & Gates                1,055 lf  $             252.00 $            266,000
            12h.3 Rolling Decorative Metal Gate                        2 ea  $       27,000.00 $              54,000
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System             34,425 sf  $                 5.40
            12i.2 Emergency Lighting             34,425 sf  $                 1.40
            12j New public address/emergency communication
            systems                            34,425 sf  $                 7.60
            12k Intrusion alarms               34,425 sf  $                 1.80 $              62,000
          13 District Support Facilities                  $                       -  $                             -
            Not included in this Facilities Needs Assessment
          14 Outdoor Learning Environments & Quads        $                       -  $                             -
            14a Main Student Quad
            14a.2 New Main Student Quad             10,000 sf  $               19.55
            14b Learning Courts
            14b.2 New Learning Court                3,200 sf  $               23.00
           15 Exterior Play Spaces, Playfields & Hardcourts  $              243,000 $                    323,000
            15a Kindergarten Play Yard                                 P2 w/ K
            15a.1 New Rubberized Surface Play Area                2,800 sf  $               20.00 $              56,000
            15a.3 Shade Structure                 1,200 sf  $               90.00 $            108,000
            15a.6 New Hardcourts                  7,200 sf  $               11.00 $              79,000
            15b PE Play Yard & Hardcourts
            15a.1 New Rubberized Surface Play Area                3,200 sf  $               20.00
            15b.3 Relocate Elementary Play Apparatus                        1 ea  $       18,000.00
            15b.4 Shade Structure                 2,400 sf  $               90.00
            15b.7 Slurry Coat & Stripe Existing Hardcourts             30,000 sf  $                 3.00
            15c Playfields
            15c.1 Repair Playfields             46,800 sf  $                 3.00
           16 Next Generation Classroom Flexibility (Furniture)  $                       -  $                             -
            16a Flexible furniture (Per Classroom, Direct Cost)                     29 ea  $       15,000.00
           17 Technology Infrastructure                   $                       -  $                             -
            Not included in this Facilities Needs Assessment


         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  612
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District