Page 636 - Facilities Master Plan 2016
P. 636

Lodi Unified School District                                            Lodi Unified School District
          Leroy Nichols Elementary School                                         Leroy Nichols Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                   19-Apr-16
                        Project Cost Summary (2016$) - Leroy Nichols Elementary School          Project Cost Summary (2016$) - Leroy Nichols Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
                                                                                   4b New Construction - Classrooms
          01 Modernize & Reconfigure Aging Classrooms      $                       -  $                             -  4b.1 Remove Portable Classrooms                        4 ea  $       11,000.00 $              44,000
            1b Replacement or repair of walls                                       4b.2 Relocate Portable Classrooms                        1 ea  $       25,000.00 $              25,000
            1b.1 Replace walls                    2,700 sf  $               39.50
            1b.2 Repair walls                  12,660 sf  $               12.60     4b.4 New Elementary Classroom Building (1-story)                5,280 sf  $             404.00 $         2,133,000
            1c Replacement or repair of windows                                     4b.10 Sitework & Site Improvements                5,280 sf  $               38.00 $            201,000
            1c.1 Replace windows               15,360 sf  $               18.00    4d Student Collaboration Lab
            1d Replacement or repair of doors (other than safety locks              4d.1 New Student Collaboration Lab, 1- Story                1,056 sf  $             395.00 $            417,000
            @ classroom doors)                                                      4d.2 Sitework & Site Improvements                1,056 sf  $               38.00 $              40,000
            1d.1 Replace doors & hardware             15,360 sf  $               13.50
            1e Replacement or repair of floors
            1e.1 Replace floors                15,360 sf  $               14.40   05 Maker Spaces & Science Labs                  $                       -  $                             -
            1f Replacement or repair of ceilings                                   5a ES Science / Creativity Labs
            1f.1 Replace ceilings              15,360 sf  $               27.00
            1g Patch & Paint Interior/Exterior                                      5a.5 Reconfigure ES Science / Creativity Labs Building                 2,880 sf  $             243.00
            1g.1 Patch & paint interior             15,360 sf  $                 3.10
            1g.2 Patch & paint exterior             15,360 sf  $                 4.50
            1o Replace Existing Roofing             35,544 sf  $               20.93  06 Electives                                $                       -  $                             -
            1p Repair Existing Covered Walkways / Hallways                5,200 sf  $               13.00  Not included in this Facilities Needs Assessment
          02 Existing Building Systems & Toilets           $              726,000 $                    966,000  07 Performing Arts Improvements  $                       -  $                             -
            2a HVAC system upgrades             15,360 sf  $               29.00   7a Music Lab
                                                                                    7a.4 New Music Lab                    1,540 sf  $             449.00
            2b Lighting upgrades - new interior lighting & controls             15,360 sf  $               15.00  7a.5 Sitework & Site Improvements                1,540 sf  $               38.00
            2c Electrical upgrades
            2c.1 Upgrade electrical wiring & increase electrical
            outlets                            15,360 sf  $                 9.00  08 Multi-Purpose Room / Food Service Improvements & Student Dining  $           1,122,000 $                 1,492,000
            2d Plumbing system upgrades             15,360 sf  $               11.00 $            169,000  Toilets  8a Elementary/Middle School multipurpose rooms  P3
            2e Replace aging plumbing, upgrade and/or expand                        8a.2 Modernize Multipurpose Room                4,000 sf  $               99.00 $            396,000
            restroom facilities                                                    8c Food service areas
            2e.2 Reconfigure Existing Restroom                2,510 sf  $             222.00 $            557,000  Toilets  8c.3 Reconfigure Food Service                1,230 sf  $             350.00 $            431,000
            2f Energy-efficient building systems and controls (EMS                  8c.5 New Kitchen Equipment                1,230 sf  $               63.00 $              77,000
            system, per sf of Bldg)             15,360 sf  $                 7.20
                                                                                    8c.6 New Trash Enclosure                        1 ea  $       45,000.00 $              45,000
                                                                                   8d New Lunch Shelters                  2,400 sf  $               72.00 $            173,000
          03 Site Utilities                                $                       -  $                             -
            (For entire campus and site)                                          09 Physical Education Improvements              $                       -  $                             -
            3a Updated gas service lines           435,600 sf  $                 0.30  9c PE/Fitness Labs
            3b Updated sewer service lines           435,600 sf  $                 0.53  9c.4 New PE/Fitness Labs                2,112 sf  $             404.00
            3c Updated water service lines           435,600 sf  $                 0.68  9c.5 Sitework & Site Improvements                2,112 sf  $               38.00
            3d Updated electrical mains and distribution           435,600 sf  $                 0.90
            3f Electrical Capacity Upgrades                        1 ls  $     115,000.00
                                                                                  10 Administration & Staff Support               $                       -  $                             -
                                                                                   10a Expanded, reorganized or relocated administration
          04 Classrooms New Construction                   $           2,860,000 $                 3,804,000  spaces
                                                                                    10a.3 Reconfigure Administration                   840 sf  $             235.00
            4a New Construction - Pre-School, DK & Kindergarten                     10a.4 New Administration                   975 sf  $             392.00
                                                                  Modular           10a.5 Sitework & Site Improvements                   975 sf  $               38.00
            4a.2 New Pre-School, DK & Kindergarten Building                1,440 sf  $             316.00  construction  10b Staff Collaboration/Work Rooms
            4a.4 Sitework & Site Improvements                1,440 sf  $               38.00
                                                                                    10b.2 Modernize Staff Collaboration/Work Rooms                   936 sf  $             118.00
                                                                                    10b.3 Reconfigure Staff Collaboration/Work Rooms                   500 sf  $             235.00
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.3       APPENDIX                                                                                                    Facilities Master Plan  607
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District
   631   632   633   634   635   636   637   638   639   640   641