Lodi Unified School District                                            Lodi Unified School District
          George Lincoln Mosher Elementary School                                 George Lincoln Mosher Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                      Project Cost Summary (2016$) - George Lincoln Mosher Elementary School  Project Cost Summary (2016$) - George Lincoln Mosher Elementary School
                                                       Construction Costs   Total Project                                      Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          09 Physical Education Improvements               $                       -  $                             -  16 Next Generation Classroom Flexibility (Furniture)  $                       -  $                             -
            9c PE/Fitness Labs                                                     16a Flexible furniture (Per Classroom, Direct Cost)                     33 ea  $         7,500.00
            9c.4 New PE/Fitness Labs                2,112 sf  $             404.00
            9c.5 Sitework & Site Improvements                2,112 sf  $               38.00
                                                                                  17 Technology Infrastructure                    $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
          10 Administration & Staff Support                $                       -  $                             -
            10a Expanded, reorganized or relocated administration
            spaces                                                                Total Construction/Project Cost (2016$)         $              153,000  $203,000
            10a.3 Reconfigure Administration                   750 sf  $             235.00
                                                                                  The following items are excluded from this budget:
          11 Library & Student Support Services            $                       -  $                             -  Utility hook-up fees & City connection fees.
            11d Learning Center                                                    Offsite work and traffic signals.
            11d.4 Reconfigure Learning Center                1,950 sf  $             237.00  Land acquisition costs.
                                                                                   Hazardous material surveys, abatement, and disposal.
                                                                                   Escalation (Costs are in 2016$ calculated to the end of the year).
          12 Safety, Security & Campus Control             $              153,000 $                    203,000
            12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000
            12e Safety locks at classroom doors                     45 ea  $             449.00 $              20,000
            12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000
            12h Fencing with controlled campus entrances
            12h.2 Decorative Metal Fencing & Gates                   165 lf  $             252.00 $              42,000
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System                4,940 sf  $                 5.40
            12i.2 Emergency Lighting                4,940 sf  $                 1.40
            12j New public address/emergency communication
            systems                               4,940 sf  $                 7.60
          13 District Support Facilities                   $                       -  $                             -
            Not included in this Facilities Needs Assessment
          14 Outdoor Learning Environments & Quads         $                       -  $                             -
            14b Learning Courts
            14b.2 New Learning Court                3,200 sf  $               23.00
           15 Exterior Play Spaces, Playfields & Hardcourts  $                       -  $                             -
            15a Kindergarten Play Yard
            15a.1 New Rubberized Surface Play Area                2,000 sf  $               20.00
            15a.3 Shade Structure                 1,200 sf  $               90.00
            15a.6 New Hardcourts                  7,200 sf  $               11.00
            15b PE Play Yard & Hardcourts
            15a.1 New Rubberized Surface Play Area                6,000 sf  $               20.00
            15b.2 Elementary Play Apparatus                        1 ea  $       63,000.00
            15b.3 Relocate Elementary Play Apparatus                        1 ea  $       18,000.00
            15b.6 New Hardcourts               32,500 sf  $               11.00



         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  602
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District
   626   627   628   629   630   631   632   633   634   635   636