Page 633 - Facilities Master Plan 2016
P. 633
Lodi Unified School District Lodi Unified School District
John Muir Elementary School John Muir Elementary School
Facilities Master Plan - Total Program Cost Facilities Master Plan - Total Program Cost
Opinion of Probable Cost 19-Apr-16 Opinion of Probable Cost 19-Apr-16
Project Cost Summary (2016$) - John Muir Elementary School Project Cost Summary (2016$) - John Muir Elementary School
Construction Costs Total Project Construction Costs Total Project
Item Quantity Unit Unit Cost Subtotal Total Cost 25% (x 1.33) Item Quantity Unit Unit Cost Subtotal Total Cost 25% (x 1.33)
12 Safety, Security & Campus Control $ 453,000 $ 602,000 Total Construction/Project Cost (2016$) $ 1,918,000 $2,550,000
12b Safety improvements to and/or new parent/bus drop-off areas and parking
12b.1 New Parking Lot 5,000 sf $ 16.00 $ 80,000
12b.5 New Drop-off Area 7,000 sf $ 18.00 $ 126,000 The following items are excluded from this budget:
12b.10 Slurry Coat & Stripe Existing Paving 19,800 sf $ 2.00 $ 40,000 Utility hook-up fees & City connection fees.
12d Exterior lighting to ensure student safety 1 ls $ 40,000.00 $ 40,000 Offsite work and traffic signals.
12e Safety locks at classroom doors 35 ea $ 449.00 $ 16,000 Land acquisition costs.
12f Signage for emergency response and wayfinding 1 ls $ 32,000.00 $ 32,000 Hazardous material surveys, abatement, and disposal.
12g Marquee Sign 1 ea $ 10,000.00 $ 10,000 Escalation (Costs are in 2016$ calculated to the end of the year).
12h Fencing with controlled campus entrances
12h.2 Decorative Metal Fencing & Gates 180 lf $ 252.00 $ 45,000
12i Fire safety equipment, fire alarms and emergency lighting
12i.1 Fire Alarm System 35,330 sf $ 5.40
12i.2 Emergency Lighting 35,330 sf $ 1.40
12j New public address/emergency communication
systems 35,330 sf $ 7.60
12k Intrusion alarms 35,330 sf $ 1.80 $ 64,000
13 District Support Facilities $ - $ -
Not included in this Facilities Needs Assessment
14 Outdoor Learning Environments & Quads $ - $ -
14b Learning Courts
14b.2 New Learning Court 2,400 sf $ 23.00
15 Exterior Play Spaces, Playfields & Hardcourts $ - $ -
15a Kindergarten Play Yard
15a.1 New Rubberized Surface Play Area 1,200 sf $ 20.00
15a.3 Shade Structure 1,200 sf $ 90.00
15a.7 Slurry Coat & Stripe Existing Hardcourts 7,200 sf $ 3.00
15b PE Play Yard & Hardcourts
15a.1 New Rubberized Surface Play Area 5,000 sf $ 20.00
15b.2 Elementary Play Apparatus 1 ea $ 63,000.00
15b.4 Shade Structure 2,400 sf $ 90.00
15b.6 New Hardcourts 14,400 sf $ 11.00
15b.7 Slurry Coat & Stripe Existing Hardcourts 28,600 sf $ 3.00
15c Playfields
15c.1 Repair Playfields 87,900 sf $ 3.00
16 Next Generation Classroom Flexibility (Furniture) $ - $ -
16a Flexible furniture (Per Classroom, Direct Cost) 25 ea $ 15,000.00
17 Technology Infrastructure $ - $ -
Not included in this Facilities Needs Assessment
Prepared by: LPA, Inc. / Cumming Prepared by: LPA, Inc. / Cumming
6.3 APPENDIX Facilities Master Plan 604
DETAILED PRIORITIZED COST ESTIMATE Lodi Unified School District