Lodi Unified School District                                            Lodi Unified School District
          Julia Morgan Elementary School                                          George Lincoln Mosher Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                     19-Apr-16  Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - Julia Morgan Elementary School       Project Cost Summary (2016$) - George Lincoln Mosher Elementary School
                                                       Construction Costs   Total Project                                      Construction Costs   Total Project
          Item                       Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          Total Construction/Project Cost (2016$)          $              265,000  $352,000  01 Modernize & Reconfigure Aging Classrooms  $                       -  $                             -
                                                                                   1b Replacement or repair of walls
                                                                                    1b.1 Replace walls                       960 sf  $               39.50
          The following items are excluded from this budget:                       1e Replacement or repair of floors
           Utility hook-up fees & City connection fees.                             1e.1 Replace floors                      960 sf  $               14.40
           Offsite work and traffic signals.                                       1f Replacement or repair of ceilings
           Land acquisition costs.                                                  1f.1 Replace ceilings                    960 sf  $               27.00
           Hazardous material surveys, abatement, and disposal.                    1g Patch & Paint Interior/Exterior
           Escalation (Costs are in 2016$ calculated to the end of the year).       1g.1 Patch & paint interior                   960 sf  $                 3.10
                                                                                  02 Existing Building Systems & Toilets          $                       -  $                             -
                                                                                   2e Replace aging plumbing, upgrade and/or expand
                                                                                   restroom facilities
                                                                                    2e.3 New Restroom                        750 sf  $             556.00
                                                                                    2e.4 Sitework & Site Improvements                   750 sf  $               57.00
                                                                                  03 Site Utilities                               $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
                                                                                  04 Classrooms New Construction                  $                       -  $                             -
                                                                                   4a New Construction - Pre-School, DK & Kindergarten
                                                                                    4a.2 New Pre-School, DK & Kindergarten Building                4,455 sf  $             395.00
                                                                                    4a.4 Sitework & Site Improvements                4,455 sf  $               38.00

                                                                                  05 Maker Spaces & Science Labs                  $                       -  $                             -
                                                                                   5a ES Science / Creativity Labs
                                                                                    5a.5 Reconfigure ES Science / Creativity Labs Building                 1,280 sf  $             243.00
                                                                                    5a.6 New ES Science / Creativity Labs Building                 1,540 sf  $             440.00
                                                                                    5a.7 Sitework & Site Improvements                1,540 sf  $               38.00
                                                                                  06 Electives                                    $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment

                                                                                  07 Performing Arts Improvements                 $                       -  $                             -
                                                                                   7a Music Lab
                                                                                    7a.4 New Music Lab                    1,540 sf  $             449.00
                                                                                    7a.5 Sitework & Site Improvements                1,540 sf  $               38.00
                                                                                  08 Multi-Purpose Room / Food Service Improvements & Student Dining  $                       -  $                             -
                                                                                   8d New Lunch Shelters                  2,400 sf  $               72.00




         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  601
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District
   625   626   627   628   629   630   631   632   633   634   635