Page 626 - Facilities Master Plan 2016
P. 626

Lodi Unified School District                                            Lodi Unified School District
          Live Oak Elementary School                                              Lockeford Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                          Project Cost Summary (2016$) - Live Oak Elementary School              Project Cost Summary (2016$) - Lockeford Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
           16 Next Generation Classroom Flexibility (Furniture)  $                       -  $                             -  01 Modernize & Reconfigure Aging Classrooms  $                       -  $                             -
            16a Flexible furniture (Per Classroom, Direct Cost)                        8 ea  $       15,000.00  1b Replacement or repair of walls
                                                                                    1b.2 Repair walls                     6,630 sf  $               12.60
                                                                                   1c Replacement or repair of windows
           17 Technology Infrastructure                    $                 32,000 $                      32,000  1c.1 Replace windows                6,630 sf  $               18.00
             17c MDF and IDF data rooms with environmental control                 1d Replacement or repair of doors (other than safety locks
            (direct cost only)                            1 ea  $       32,000.00 $              32,000  @ classroom doors)
                                                                                    1d.1 Replace doors & hardware                6,630 sf  $               13.50
                                                                                   1e Replacement or repair of floors
          Total Construction/Project Cost (2016$)          $           7,827,000  $10,399,000  1e.1 Replace floors                6,630 sf  $               14.40
                                                                                   1f Replacement or repair of ceilings
                                                                                    1f.1 Replace ceilings                 6,630 sf  $               27.00
          The following items are excluded from this budget:                       1g Patch & Paint Interior/Exterior
           Utility hook-up fees & City connection fees.                             1g.1 Patch & paint interior                6,630 sf  $                 3.10
           Offsite work and traffic signals.                                        1g.2 Patch & paint exterior                6,630 sf  $                 4.50
           Land acquisition costs.                                                 1o Replace Existing Roofing             10,624 sf  $               20.93
           Hazardous material surveys, abatement, and disposal.                    1p Repair Existing Covered Walkways / Hallways                2,110 sf  $               13.00
           Escalation (Costs are in 2016$ calculated to the end of the year).
                                                                                  02 Existing Building Systems & Toilets          $                       -  $                             -
                                                                                   2a HVAC system upgrades                6,630 sf  $               29.00
                                                                                   2b Lighting upgrades - new interior lighting & controls                6,630 sf  $               15.00
                                                                                   2c Electrical upgrades
                                                                                    2c.1 Upgrade electrical wiring & increase electrical
                                                                                    outlets                               6,630 sf  $                 9.00
                                                                                   2d Plumbing system upgrades                6,630 sf  $               11.00
                                                                                   2e Replace aging plumbing, upgrade and/or expand
                                                                                   restroom facilities
                                                                                    2e.2 Reconfigure Existing Restroom                1,360 sf  $             222.00
                                                                                   2f Energy-efficient building systems and controls (EMS
                                                                                   system, per sf of Bldg)                6,630 sf  $                 7.20
                                                                                  03 Site Utilities                               $                       -  $                             -
                                                                                   (For entire campus and site)
                                                                                   3a Updated gas service lines           418,176 sf  $                 0.40
                                                                                   3b Updated sewer service lines           418,176 sf  $                 0.67
                                                                                   3c Updated water service lines           418,176 sf  $                 0.86
                                                                                   3d Updated electrical mains and distribution           418,176 sf  $                 1.08
                                                                                   3e Updated storm drainage system           418,176 sf  $                 0.86
                                                                                   3f Electrical Capacity Upgrades                        1 ls  $     230,000.00
                                                                                  04 Classrooms New Construction                  $           2,368,000 $                 3,149,000
                                                                                   4b New Construction - Classrooms                    (4) CR    P2
                                                                                    4b.1 Remove Portable Classrooms                        4 ea  $       11,000.00 $              44,000
                                                                                    4b.4 New Elementary Classroom Building (1-story)                4,224 sf  $             404.00 $         1,706,000
                                                                                    4b.10 Sitework & Site Improvements                4,224 sf  $               38.00 $            161,000



         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  597
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District